Introduction
This article considers the extent to which the common law now provides
helpful guidance on what are, or are not, the appropriate principles
and techniques for the demonstration of the nexus between cause
and effect in the context of construction delay claims. The material
herein is based largely on parts of a dissertation1 developed
from two articles previously written on this subject by one of the
authors hereof, which articles were published in the Construction
Law Review in 20022 and 2003,3 and on
a paper delivered by the other author.4
The use of critical path analysis techniques in proof of delay
claims is a relatively recent innovation. The use of these techniques
in relation to the demonstration and proof of delay claims and the
issues associated therewith is still a developing area of the common
law. Part of this development has arisen from the need for courts
(and other tribunals) to adapt to the new techniques made so accessible
by computer. However, few cases have dwelt upon the use of the techniques
used to demonstrate delay and their usefulness in making a successful
claim at law.
This is almost certainly because, until relatively recently, the
standard forms of contract almost invariably included arbitration
clauses, which meant that disputes about delay claims would be referred
to arbitration and, in most cases, the dispute thereby resolved.
Since May 1, 1998, however, when the Housing Grants, Construction
and Regeneration Act 1996 (''the 1996 Act'') came into force, the
majority of delay claims have been resolved by adjudication.
Although the recent cases concerning delay analysis cover a variety
of issues relevant to delay analysis, this article focuses primarily
on the extent to which the English common law assists in addressing
the central question: ''By what means does the contractor go about
proving that the delays complained of will, or have, affected the
completion date in a manner which is persuasive and yet proportionate
to the matter in dispute?''5 In so doing, this article
will seek to examine the approaches to delay claims which appear
to have found approval with the courts and those which have not.
First, however, the authors will briefly consider the contractual
mechanisms in some of the commonly used standard forms of contract,
which provide the contractual basis for claims for delay and which
give rise to some of the issues examined later in this article.
Extension of time provisions in some of the standard forms of
contract
Before one considers whether delay analysis is necessary, or
which particular method is appropriate, the first thing that has
to be done is to look at the contract. This is clearly a vital yet
sometimes overlooked step. As often explained, an extension of time
provision is a purely contractual mechanism designed to preserve
the employer's entitlement to liquidated damages and to provide
some additional allocation of risk in order to provide for ways
in which certain foreseeable types of delaying event are to be dealt
with in the event that they arise. There is nevertheless likely
to be a close connection between making a claim for delay and recovering
the additional costs incurred by the contractor associated with
that delay. Delay claims are therefore of considerable commercial
importance to contractors.
The standard JCT form of building contract 1998 edition (''JCT
98'')
JCT 98 is administered by an architect, who is appointed by
the employer and acts as his agent, but is required to act fairly
and reasonably towards the contractor when exercising his or her
powers and duties under the contract. Extensions of time are dealt
with under this form of contract at cl.25. Clause 25.4 provides
a list of 18 categories of delay, which are known as ''relevant
events'' that give rise to an entitlement to apply for an extension
of time in the event that they occur. The principal steps leading
to an extension of time as set out in the clause are as follows:
- When it becomes apparent that the progress of the works is
being or is likely to be delayed then the contractor shall notify
the architect of the cause of delay and identify whether in his
opinion it is a relevant event.
- The contractor is required to provide with the notice, or as
soon as possible after the notice, particulars of the expected
effects of the event and an estimate if any of the expected delay
to the completion of the works beyond the completion date.
- Upon receipt of the notice and any further particulars the
architect is required to decide whether in his opinion any of
the events notified are Relevant events and whether as a result
of such events the works are likely to be delayed beyond the completion
date. If he so decides, he is then required to give an extension
of time to the contractor in writing as he then estimates to be
fair and reasonable.
It is worth here emphasising the nature of the obligation on the
part of the architect, since this is considered later in this article.
The architect is required to apply some degree of discretion in
deciding what is ''fair and reasonable''. In addition, it is not
a condition of the entitlement to an extension of time that the
event has caused delay to the ''Completion Date''. It merely requires
the architect to form the opinion that as a consequence of the event
''the completion of the Works is likely to be delayed thereby beyond
the Completion Date''.
This whole procedure is quite clearly intended to be carried out
before the completion date since reference is made to the contractor
notifying the expected effect of the event, not necessarily the
actual effect of the event. The architect is then required to make
a fair and reasonable estimate of the likely effect on the completion
date, not wait until the completion date has arisen to determine
the precise effect.
In practice, it is quite often the case that the architect will
wait for full particulars of the actual effect of the event before
making a decision, by which time the event and its consequences
may be long past and the actual effect may be measured with greater
certainty. It is quite common for architects to wait until after
completion before making such grants of extension of time, but this
is clearly not what the clause intended. The probable reason for
this is that, once granted, an extension of time cannot be taken
away unless works are omitted from the contract sum and it is fair
and reasonable to reduce the time for completion of the works as
a consequence of the omission. This almost certainly leads architects
to err on the side of caution by avoiding awarding the contractor
too much time.
There is in addition a 12-week review period which commences upon
practical completion of the works in which the architect is required
to review the extensions of time granted to the contractor and take
account of any other relevant events that he is aware of, whether
or not they have been notified by the contractor. Earlier extensions
cannot be reduced unless critical works have been omitted since
the previous extension of time. In accordance with cl.25.3.3.1,
the architect is required to
'' fix a Completion Date later than that previously fixed if in
his opinion the fixing of such later Completion Date is fair and
reasonable having regard to any of the Relevant Events... ''.
It is also worth emphasising that this clause makes no mention of
the requirement for events to have affected the completion date. This
is therefore a different sort of assessment, and there is potentially
even greater discretion available to the architect in deciding on
extensions of time at this stage. However, by this time the works
will in fact have been completed and the overall effect of all the
delaying events on the project will be known. This overall final assessment
is therefore likely to be based on a consideration of what has actually
happened.
There is a possible tension between the two positions since any review
on the basis of what actually happened cannot be used to reverse an
earlier decision that was made on the basis of the likely effect of
events on the completion date
The ICE conditions of contract, measurement version, 7th edition,
September 1999 (''ICE 7th'')
ICE 7th is administered by an engineer, who is appointed by the
employer and acts as his agent, and is required to act fairly towards
the contractor. This form of contract provides an entitlement to extensions
of time under a number of clauses, but the principal provisions for
dealing with extensions of time are set out at cl.44 as follows:
- If one of the listed types of delay occurs, then within 28
days after the cause of delay has arisen or as soon thereafter
as is reasonable deliver to the engineer full and detailed particulars
in justification of the period of extension claimed in order that
the claim may be investigated at the time (cl.44(1)).
The engineer is then required to make an assessment of
the delay, having regard to all the circumstances known to him
at the time, whether or not the contractor has made a claim (cl.44(2)).
-
If the engineer considers that the delays suffered fairly
entitle the contractor to an extension of the time for substantial
completion of the works then he grants the extension to the contractor
in writing (cl.44(3)).
-
Not later than 14 days after the due date or extended
date for completion, the engineer is then required to make a further
interim assessment based on all the circumstances known to him
at the time and whether or not the contractor has made a claim
(cl.44(4)).
In a similar fashion to the JCT contract, cl.44(5) provides for a
final review by the engineer of all matters that might entitle the
contractor to an extension of time, which review is to be carried
out within 28 days of the issue of the certificate of substantial
completion. Also as with the JCT form, this final review may not result
in a decrease in any extension of time already granted by the engineer.
In Keating on Building Contracts (7th ed.),6 it
is observed that this is in contrast to the assessment in cl.44(4)
at the due date, which may reduce extensions previously granted.
Thus, although the wording and the timescales are different, the underlying
principles are very similar to the JCT contract, and again the intention
is that extensions of time should be granted as the work proceeds.
The principal distinction between the contracts, however, is that
the penultimate review under ICE 7th can be a complete retrospective
review of all matters, and will therefore be concerned with what by
that stage has actually happened.
The engineering and construction contract, second edition, November
1995 (''ECC'')
The ECC is administered by a project manager, and under this form
the programme assumes greater importance than under the other forms.
There is no separate extension of time provision, but, instead, the
contract provides for compensation events in accordance with core
cl.6. Clause 60.1 lists 18 types of compensation event and provides
the procedure for notifying, assessing and implementing compensation
events as follows:
- The project manager may notify the contractor of a compensation
event at the time of the event, where the event arises from the
project manager, and request the contractor to provide a quotation
for the compensation event.
- The contractor otherwise notifies the project manager of any
compensation event which has happened, or which he expects to
happen, within two weeks of becoming aware of any such event.
- In order for the prices and/or the completion date to
be changed, the project manager must decide that the event has
not arisen from any default of the contractor, that it is a compensation
event, and that it will have an effect on actual cost or completion,
in which case he requests the contractor to submit a quotation.
- The contractor's quotation is required to include an
assessment by the contractor of any proposed changes to the prices
and any delay to the completion date as a result of the event.
If the programme for the remaining work is affected by the compensation
event, the contractor is required to include a revised programme
showing the effect.
- The project manager may accept the quotation, request
the contractor to submit a revised quotation or carry out his
own assessment.
- A delay to the completion date is assessed by the project
manager as the length of time that, owing to the compensation
event, planned completion is later than planned completion shown
on the accepted programme.
- A compensation event is implemented when the project
manager accepts the quotation from the contractor or provides
him with his own assessment.
- An assessment of a compensation event may not subsequently
be revised if a forecast upon which it was based is later shown
to be wrong, unless the project manager decides that the effects
of an event are too uncertain to be forecast reasonably, in which
case he states the assumptions on which the quotation and the
assessment is to be based. If his assumptions are later found
to be wrong, the project manager may notify a correction.
This is therefore quite a different procedure from that contained
within the JCT and ICE forms of contract. Central to this contract
philosophy is the notion of identifying and assessing the effect of
delaying events at the time at which they occur and reflecting them
on an updated programme. There is no provision for a final review
of extensions of time previously granted.
Thus what all these contracts have in common is the intention that
delaying events will be identified and an assessment made of their
effect at the time they occur, and that to give rise to an extension
of time the delaying event must be expected to affect the completion
date. The JCT and ICE contracts in addition provide for a period of
nal review of extensions of time after completion, thus requiring
an after-the-event assessment of the effect of the various delaying
events in the knowledge of what actually happened.
The effect of a delay in a period of culpable delay
It is worth briefly noting here that the case of Balfour Beatty
v Chestermount7 is one which establishes a very important
principle in considering any entitlement to extensions of time and
which, in the authors' opinion, represents a common sense approach
to the issue, namely that cl.25.3 of JCT 80 was wide enough to include
relevant events which occurred after as well as before any previously
fixed completion date, and also that when considering delay events
which occur in a period of culpable delay, the contractor will be
entitled to an extension of time on the net method of extension (sometimes
referred to as the ''dot on'' principle), which allows the incremental
time lost for the new event to be added back to the previously extended
completion date, rather than allowing an extension of time to the
date on which the late instructed work is completed. In other words,
the gross method of extension was disapproved. As Nicholas Carnell8
has observed:
''In the context of the power to review it was contended that on
a proper construction of clause 25.3.3, the power to review could
only be exercised to grant the new completion date at a future
date. Mr Justice Colman rejected this proposition, and held that
the duty was to review the net extension to which the contractor
was due, and that this could in many instances result in the completion
date being fixed at a date prior to the date on which the
review had taken place.''
Thus the architect was and is not precluded from making a retrospective
assessment of delay.
A brief examination of causation and concurrent delay
The claimant is under the legal and evidential burden of proving
the nexus between the event, or the cause, and the delay to completion,
or the effect. The contractor must therefore demonstrate cause and
effect. Questions of causation commonly arise in both contract and
tort cases, but the authors have limited this part of this article
to a review of the recent developments concerning the determination
of entitlement to extensions of time where questions of concurrent
delay arise.
The courts now generally favour the ''common sense'' approach to dealing
with matters of causation. However, this does not provide a very helpful
answer to how liability will be allocated between competing causes
where one of the causes is not the fault of either party or is a delay
for which, in breach of contract, the contractor is responsible. There
are a number of shipping cases concerning insurance claims which support
the application of the dominant cause approach. Indeed this is the
approach preferred by Keating on Building Contracts, which
says:
''The dominant cause approach is supported as indicated above by authority
of great weight in insurance cases. It is thought that the principles,
so far as they apply, apply to contracts generally. It is accordingly
submitted that the dominant cause approach is or should be the correct
approach, as the law now stands, for Case C and for case B also, unless
exceptionally the contract on its true construction provides an explicit
answer without sophisticated analysis.''9
Case B, as postulated by Keating on Building Contracts,10
concerns claims for payment under the contract for delay resulting
from variation instructions where there is a competing cause of delay
which could be no one's fault or the contractor's own delay in breach
of contract. Case C provides for the same situation but where the
contractor is instead claiming damages for breach of contract.
Keating on Building Contracts11 does, however, observe
that in H Fairweather & Co v London Borough of Wandsworth12
the court considered obiter that the dominant cause approach was not
correct. This case concerned an arbitration under the JCT 63 form
of contract, in which the arbitrator had applied the dominant cause
approach to deciding that a strike causing 81 weeks of delay was dominant
and that no time should be allocated to the 18 weeks of antecedent
delays claimed by the contractor. His Honour Judge Fox-Andrews Q.C.
remitted the relevant part of the award to the arbitrator, stating:
'' 'Dominant' has a number of meanings: 'Ruling, prevailing, most
influential.' On the assumption that condition 23 is not solely
concerned with liquidated or ascertained damages but also triggers
and conditions a right for a contractor to recover direct loss and
expense where applicable under condition 24 then an architect and
in his turn and arbitrator has the task of allocating, when the
facts require it, the extension of time to the various heads. I
do not consider that the dominant test is correct. But I have held
earlier in this judgement that the assumption is false. I think
the proper course here is to order that this part of the interim
award should be remitted to Mr Alexander for his reconsideration
. . . .''
In his article on concurrent delay, John Marrin Q.C.13 observes that,
in light of the particular terms of the JCT contract and the fact
that the architect has discretion to determine contractual entitlement
to extensions of time, it would be most unlikely that the architect
would deprive the contractor of an extension of time in respect of
the particular period if that contractor had a right to recover loss
and expense in respect of the same period. He goes on to say that
it is thought that the problem envisaged will virtually never occur
and that for these reasons the courts in England are unlikely to adopt
the dominant cause approach.
So how is the situation to be resolved where there is a concurrent
effect contributed to equally by two competing causes, such as for
example where the employer has delayed the work by instructing additional
work, but where the contractor is in culpable delay?
The problem with the dominant cause approach, as indicated by the
Fairweather case, is that it necessarily requires a choice
to be made between one cause or another. Given that the standard forms
of contract allow the contractor an extension of time and loss and
expense or costs for employer-caused delay and the employer is entitled
to liquidated damages for contractor-caused delay, the dominant cause
approach will inevitably lead to injustice to one of the parties.
In this situation, why should the employer be entitled to liquidated
damages for his own default, and why should the contractor be entitled
to loss and expense for his own default? It would be consistent with
the decision in Peak v McKinney14 for the employer not to be
entitled to liquidated damages.
An approach to dealing with this conundrum was first addressed in
the case of Henry Boot Construction (UK) Ltd v Malmaison Hotel
(Manchester) Ltd,15 which Dyson J. was required to
determine an appeal on pleadings, concerning the extent of the arbitrator's
jurisdiction to inquire into one of the contractor's extension of
time claims. The judge set out in his judgment various areas of common
ground between the parties, including:
'' . . . it is agreed that if there are two concurrent causes of delay,
one of which is a Relevant Event, and the other is not, then the contractor
is entitled to an extension of time for the period of delay caused
by the Relevant Event notwithstanding the concurrent effect of the
other event. Thus, to take a simple example, if no work is possible
on the site for a week not only because of exceptionally inclement
weather (a Relevant Event), but also because the contractor has a
shortage of labour (not a Relevant Event), and if the failure to work
during that week is likely to delay the Works beyond the Completion
Date by one week, and if he considers it fair and reasonable to do
so, the Architect is required to grant an extension of time of one
week. He cannot refuse to do so on the grounds that the delay would
have occurred in any event by reason of the shortage of labour.''16
Malmaison was considered, and further support was given to
this approach by His Honour Judge Seymour Q.C. (in a judgment later
referred to by the Court of Appeal as exemplary) in the case of The
Royal Brompton Hospital NHS Trust v Hammond (No.7)17
at [85] of his judgment, where he said:
''However, if Taylor Woodrow was delayed in completing the works both
by matters for which it bore the contractual risk and by Relevant
Events, within the meaning of that term in the Standard Form, in light
of the authorities to which I have referred, it would be entitled
to extensions of time by reason of the occurrence of the Relevant
Events notwithstanding its own defaults.''
John Marrin concludes that, in dealing with competing employer and
contractor caused delay referred to above, the main contenders are
the dominant cause approach and Malmaison approach and that
the Malmaison approach is to be preferred.
The authors believe that the present state of English law on the subject
of concurrent culpable delay is accurately and succinctly summarised
in the following paragraphs of the decision of His Honour Judge Toulmin
Q.C. CMG in Motherwell Bridge Construction Ltd v Micafil Vakuumtechnik18:
''The law
[559] The law relating to extensions of time as a result of delay
by the employer has been clarified in two cases-Balfour Beatty
Building Ltd v Chestermount Properties (1993) 32 ConLR 139.
[560] The basic principle is encapsulated in para 12 of Dyson J's
judgment in Henry Boot (70 ConLR 32 at 37):
'First, it is agreed that the analysis of Colman J in Balfour
Beatty Building Ltd v Chestermount Properties (1993) 32 Con
LR 139, should be applied. In his valuable interpretation of cl
25 of this form of contract, Colman J said, inter alia, that the
purpose of the power to grant an extension of time under cl 25.3
was to fix the period of time by which the period of time available
for completion ought to be extended having regard to the incidence
of the relevant events, measured by the standard of what is fair
and reasonable. The completion date as adjusted was not the date
by which the contractor ought to have achieved practical completion,
but the end of the total number of working days starting from
the date of possession within which the contractor ought fairly
and reasonably to have completed the works.'
[561] In Henry Boot, Dyson J dealt with the questions of
concurrent delays and whether it is permissible to consider other
events. In relation to the first question Dyson J said, at para
13 of his judgment (70 ConLR 32 at 37):
'Second, it is agreed that if there are two concurrent causes
of delay, one of which is a relevant event, and the other is not,
then the contractor is entitled to an extension of time for the
period of delay caused by the relevant event notwithstanding the
concurrent effect of the other event. Thus, to take a simple
example, if no work is possible on a site for a week not only
because of exceptionally inclement weather (a relevant event),
but also because the contractor has a shortage of labour (not
a relevant event), and if the failure to work during that week
is likely to delay the works beyond completion date by one week,
then if he considers it fair and reasonable to do so, the architect
is required to grant an extension of time of one week. He cannot
refuse to do so on the grounds that the delay would have occurred
in any event by reason of the shortage of labour.'
In relation to the second question, Dyson J held that an architect
is not precluded from considering the effect of other events when
determining whether a relevant event is likely to cause delay to
the works beyond completion.
[562] In the course of Mr Pye's evidence I made a number of rather
off the cuff observations in relation to the causes of delay. I
am satisfied that my approach must be that outlined in the passages
from the judgment in the Henry Boot case which I have set out above.
Crucial questions are (a) is the delay in the critical path and,
if so, (b) is it caused by MBST? If the answer to the first question
is 'Yes' and the second question is 'No' then I must assess how
many additional working days should be included. If the alleged
delay was caused by the default of MBST then they are not entitled
to any extension of time.
[563] Other delays caused by MBST (if proved) are not relevant since
the overall time allowed for under the contract may well include
the need to carry out remedial works or other contingencies. These
are not relevant events since the court is concerned with considering
extensions of time within which the contract must be completed.
[564] I add that the approach must always be tested against an overall
requirement that the result accords with common sense and fairness.''
(emphasis added)
Malmaison and Brompton do not appear to deal specifically
with the entitlement to loss and expense, although it would seem to
follow that, where the contractor is in concurrent culpable delay,
he will only be entitled to recover the specific additional costs
incurred as a result of employer's delay, which because of the contractor's
default will exclude his general time-related costs. It is noted that
this is the approach adopted by the SCL Protocol (2002).19
This approach to dealing with loss and expense in relation to concurrent
delay has found support from Lord Drummond Young in the Scottish
Inner House Court of Session case of John Doyle Construction
Ltd v Laing Management (Scotland) Ltd (2004). Paragraphs [10]
to [20] of the judgment consider the question of ''causation of
loss and global claims'', paras [14] to [17] in particular dealing
with causation and the apportionment of loss in various circumstances,
including situations of concurrent delay. Relevant extracts are
as follows:
''[14]... In the first place, it may be possible to identify
a causal link between particular events for which the employer
is responsible and individual items of loss. On occasion that
may be possible where it can be established that a group of events
for which the employer is responsible are causally linked with
a group of heads, provided that loss has no other significant
cause. In determining what it is a significant cause, the 'dominant
cause' approach described in the following paragraph is of relevance...
[15] . . . In the second place, the question of causation must
be treated by 'the application of common sense to the logical
principles of causation' ... In this connection, it is frequently
possible to say that an item of loss has been caused by a particular
event notwithstanding that other events played a part in its occurrence.
In such cases, if an event or events for which the employer is
responsible can be described as the dominant cause of an item
of loss, that will be sufficient to establish liability, notwithstanding
the existence of other causes that are to some degree at least
concurrent . . .
[16] In the third place, even if it cannot be said that events
for which the employer is responsible are the dominant cause of
the loss, it may be possible to apportion the loss between the
causes for which the employer is responsible and other causes.
In such a case it is obviously necessary that the event or events
for which the employer is responsible should be a material cause
of the loss. Provided that condition is met, however, we are of
opinion that apportionment of loss between the different causes
is possible in an appropriate case. Such a procedure may be appropriate
in a case where the causes of the loss are truly concurrent, in
the sense that both operate together at the same time to produce
a single consequence. For example, work on a construction project
might be held up for a period owing to the late provision of information
by the architect, but during that period bad weather might have
prevented work for part of the time. In such a case responsibility
for the loss can be apportioned between the two causes, according
to their relative significance. Where the consequence is delay
as against disruption, that can be done fairly readily on the
basis of the time during which each of the causes was operative.
During the period when both operated, we are of opinion that each
should normally be treated as contributing to the loss, with the
result that the employer is responsible for only part of the delay
during that period. Unless there are special reasons to the contrary,
responsibility during that period should probably be divided on
an equal basis, at least where the concurrent cause is not the
contractor's responsibility. Where it is his responsibility, however,
it may be appropriate to deny him any recovery for the period
of delay during which he is in default.''
This case indicates, at least in the context of financial losses arising
from loss events, a preference in the first place for a common sense
approach to identifying the dominant cause of the loss and then, in
the absence of a dominant cause, some sort of apportionment of loss.
However, in common with the SCL Protocol approach, it is suggested
that, where the contractor's own culpable delay is concurrent in effect,
then the contractor may be denied recovery of loss for that period.
This has a very important bearing on how delay claims and the resultant
costs are analysed. For the purpose of determining the contractor's
entitlement to loss and expense, it is necessary to distinguish
periods of delay where the employer's action is the sole (or dominant)
cause of the delay from those where there is a concurrent default
on the part of the contractor.
It is important to emphasise the distinction between a matter which
would entitle the contractor to an extension of time under the contract,
such as a relevant event in accordance with JCT 98, from a matter
which actually causes delay to completion of the work. For example,
it is tempting for a contractor to argue that information issued
late by the architect, relative to the information release schedule,
notwithstanding the general progress on site, will be a concurrent
delay for which the contractor should receive an extension of time.
The contractor will only be entitled to an extension of time where
the event affects the completion date, and only to the extent that
it causes incremental delay to the completion date, rather than
to the extent by which information is late relative to the information
release schedule. This point was emphasised in the Brompton
case.20
There is then a clear distinction between concurrent cause and
concurrent effect. Indeed, it is noted that this distinction is
recognised in the extension of time provisions (cl.12) in the JCT
Major Projects Form of contract, which specifically provides for
the entitlement of the contractor to an extension of time notwithstanding
the fact that there may have been a ''concurrent in effect of a
cause'' for which there is no entitlement to an extension of time,
i.e. the contractor's own culpable delay.
A resource-based quantification of delay
Construction projects are invariably highly labour-intensive, and
so when one is looking to establish a measure of delay and its effect,
one is almost certainly involved in considering the availability
of resources to cope with additional or changed work and the effect
of such changes on that resource. In the absence of very clear records,
it may be necessary to make an approximation of the impact of delay
on the available resources. Here lies a danger. If one takes, by
way of an example, a variation for some additional joinery work
which occupies two joiners for one week, then the delay to those
two joiners is one week. If the particular work they are engaged
in happens to be entirely critical then this would equate to a critical
delay of one week to the completion date. But what happens if the
work is not obviously critical but simply represents an increase
in scope of work for that particular trade? The first point is that
one has to demonstrate that this particular trade was critical at
the time of the event. One then has to establish a measure of extent
of the effect of that particular delay on the critical path.
It is not unusual for those who are involved in making claims for
delay to inflate the claim by overstating the effect of an event
by equating the effect of the delay to the specific resources engaged
in the additional work rather than the effect on all the resources
engaged in that particular trade at that point in time. This was
precisely the manner in which the expert witness for the claimant
approached the quantification of delay in the case of McAlpine
Humberoak Ltd v McDermott International Inc (No.2),21
in which Lloyd L.J. stated as follows:
'' . . . he went through each of the VOs, and arrived at a number
of days or weeks, based either on the time actually taken to carry
out the extra work or on a calculation . . .
With perfect logic, he added a claim for night working, for his
method of calculation assumed the same work force working one night
shift throughout, as originally planned without any night shift
. . .
One cannot help admiring the way in which [the expert witness] set
about his task. It may be that there was no other way in which it
could have been done. But it suffers from two major defects. So
far as the first stage of calculation is concerned, [the expert's]
approach assumed that if one man was working for one day on a particular
VO, the whole contract was held up for that day. The point can be
illustrated by VO 64, described by [D's counsel] as the reductio
ad absurdum of [the expert's] method. The claim was for £39,
being the cost of an inspector carrying out a lamination check on
one of the secondary tees on W3. The inspection was carried out
on 12 May 1982. It took no more than an hour. Yet [the expert] has
allowed the whole day's delay to the whole of the work.
The second, and even more serious defect relates to the second stage
of the calculation. It assumes that the whole of the workforce planned
for a particular activity was engaged continuously on that activity
from the day it started to the day it finished. This was hardly
likely to be so, quite apart from the labour difficulties which
the plaintiff suffered in phases 2 and 3 of the contract and the
decision by the plaintiff towards the end of the contract to run
down the labour force.''
A similarly flawed approach to the calculation of delay was advanced
in the case of Ascon Contracting Ltd v Alfred McAlpine Construction
Isle of Man Ltd.22 His Honour Judge Hicks Q.C. stated
(at para.[20]) as follows:
''[The expert's] second main technique was to translate cumulative
hours recorded on daywork sheets as spent on salt washing or mud
clearing into equivalent working days and to treat those as further
justification for attributing that part of the days lost to water
ingress. Again, however, that conclusion simply does not follow.
First, the labourers involved in those activities were only a part,
and usually a small part, of the work force, the rest of which was
not necessarily idle (and indeed, so far as the records have been
examined with this point in mind, was usually not so in fact), so
even in purely arithmetical terms and logic is flawed if an hour
spent by, say, one or two labourers is equated with an hour lost
to the whole project. Second, time lost in this way could in principle
be made up by late working (as, again, often seems to have happened
in practice). Third, it is wrong in principle to 'carry forward'
a part day if the next element on the critical path is a concrete
pour. A pour, once embarked upon, must be completed before the end
the working day. Either it is commenced on the due date, however
late, and completed, or it has to be postponed by a complete day
or days; there simply cannot be a part-day loss on that score to
be added to other part days.''
Judge Hicks was not persuaded that either party had satisfied the
burden of proof in relation to their allegations about the delays
and observed that he was left largely to his ''own devices''. His
starting point for assessing the measure of delay was to find that
two labourers were engaged for 105 hours on the delay work, which
equated to 50 elapsed hours, but when spread over the average labour
force of about 10 he assessed that the delay would have been a little
over one day. However, he observed that one day was too low, because
it wrongly assumed that, apart from the diversion of the labourers
directly involved, perfect efficiency could be maintained. He allowed
three days for the delay.
From the consideration of both of these cases, it is clear that, when
making such an assessment of the effect of an event on a small part
of the labour force, one must also have regard (where appropriate)
to the entire labour force available for that type of work at that
particular time.
Case law in which delay analysis methodologies are considered.
The first notable case in which delay analysis techniques were considered
was the Court of Appeal decision in McAlpine Humberoak Ltd v McDermott,23
in which the expert witnesses for the plaintiff sub-contractor (McAlpine)
and the defendant main contractor (McDermott) both used critical path
analysis techniques to analyse the effect of delays in the provision
by McAlpine of nine steel pallets forming part of the weather deck
for a tension leg off-shore platform. The Court of Appeal overturned
the decision at first instance that the contract had been frustrated
by the number of instructions issued to the plaintiff. At first instance,
McAlpine's expert carried out a somewhat theoretical exercise which
appears to have assumed that all the delay he had identified in relation
to each instruction was critical and impacted in full upon the completion
date without considering the event in the context of what was actually
happening at the time and without considering what other work was
being carried out at that time. McDermott by contrast took a much
more fact-based approach to the analysis of delay, about which Lloyd
L.J. said as follows:
''When the defendant's witnesses came to give evidence, they undertook
the task which was never undertaken by the plaintiff, of tracing
the impact of every drawing revision, VO and TQ. . . The judge [at
first instance] dismissed the defendants' approach to the case as
being 'a retrospective and dissectional reconstruction by expert
evidence of events almost day by day, drawing by drawing, TQ by
TQ and weld procedure by weld procedure, designed to show that the
spate of additional drawings which descended on McAlpine virtually
from the start of the work really had little retarding or disruptive
effect on its progress'. In our view the defendants' approach is
just what the case required.''24
This provided guidance in relation to the proper approach to be taken
to these situations. The analysis must primarily be a factual one
that shows what actually happened, so that the events and their effects
should be examined at the time they occur in the context of the work
actually going on at the time. This therefore relies on good records
being available to support the claim.
In the case of Henry Boot Construction (UK) Ltd v Malmaison Hotel
(Manchester) Ltd,25 which considers the operation of
cl.25 under the JCT 80 standard form, it was held by Dyson J. (as
he then was) that
''The respondent was entitled to respond to the claim both by arguing
that the variations, late information and so on relied on by the claimant
did not cause any delay because they were not on the critical path
and positively by arguing that the true cause of delay was other matters''.
This confirms the view that, in order to establish that an event has
affected the completion date, it must be shown that it falls on the
critical path.
In Motherwell Bridge Construction Ltd v Micafil Vakuumtechnik, discussed
above, Judge Toulmin provided, at para.[562], yet further confirmation
of the requirement to establish the critical path:
''Crucial questions are (a) is the delay in the critical path and,
if so, (b) is it caused by MBST? If the answer to the first question
if 'Yes' and the second question is 'No' then I must assess how
many additional working days should be included.''
Some means by which the critical path can be identified and shown
is therefore required. Although the emphasis appears to be on an examination
of what actually happened, neither of the above passages makes it
clear whether the critical path being referred to is the apparent
critical path at the time of the event or the ultimate overall as
built critical path evident at the completion of project.
The passage from Henry Boot referred to above also points to
some of the principal defences to a delay claim. In order to show
that an event was not on the critical path, the defendant has to argue
that the claimant's version of the critical path is incorrect and
must prove on the balance of probabilities that the critical path
in fact went elsewhere. Of course, it will also be appropriate to
investigate whether on the facts the event actually caused a delay
and whether it had any consequential effects, as well as looking for
other events that may have driven progress at that time and therefore
have been the true causes of delay. A claimant when faced with such
a defence should not make the mistake of assuming that, if the defendant
fails to satisfy the legal and evidential burdens of proof in favour
of its alternative view of things, then the claimant's allegation
of the true cause of delay must be accepted by default. This sort
of argument was not accepted by Judge Hicks in the case of Ascon
Contracting Ltd v Alfred McAlpine Construction Isle of Man Ltd,26
where he stated at para.[21] that
''It is Ascon which is seeking an extension of time and must establish
a cause of a quantified period of delay entitling it to that extension''.
Most disputes about extensions of time arise after the works are complete
and often, at least under the JCT 98 and ICE 7th forms of contract,
once the architect or engineer has completed his final review of the
extensions of time due to the contractor. The dispute in such circumstances
is about the overall extension of time granted as a result of the
final review process. The task for the court (and therefore for the
expert witnesses) is more likely to involve looking at what actually
happened, therefore requiring some sort of as-built programme.
In the case of Henry Boot Construction (UK) Ltd v Malmaison Hotel
(Manchester) Ltd,27 which considers the operation of
cl.25 under the JCT 80 standard form of contract, Dyson J. stated
at para.[15] that
''It seems to me that it is a question of fact in any given case whether
a Relevant Event has caused or is likely to cause delay to the Works
beyond the Completion Date... ''.
This is where extension of time claims can go wrong. The basic factual
matrix is often not sufficiently established or understood when the
claim is prepared, with the result that the proper context in which
an event occurred is often ignored when alleging that an event has
delayed the completion date. This is before deciding whether anything
can be added by the use of critical path analysis.
The above passage indicates that the courts are concerned primarily
with what has actually happened rather than considering any sort of
analysis that may be based on some speculation about what would or
could have been the effect at the time the event occurred. The view
has been expressed by some commentators that judges and arbitrators
are really looking to get into the facts in order to find out what
really happened on the site and to identify the real causes of delay.
It is important to recognise that there is a distinction between what
really caused delay and a contractor's entitlement to an extension
of time in accordance with the terms of the contract.
It is also worth adding that, when faced with difficult situations
of causation or (by analogy) difficult-to-understand prospective delay
analyses, the courts are likely to adopt a ''common sense'' approach28
to deciding a matter, which is likely to be informed, not by what
might have happened, but by a common sense approach to what actually
happened.
On the other hand, a the use of a forward-looking or prospective method
of delay analysis, such as time impact analysis, which identifies
the expected effect of an event at the time it occurred, overcomes
the problem that commonly occurs in reality, namely that the effect
of an event is often subsumed or overtaken by subsequent events.
In addition, adjudication has made the resolution of disputes on an
interim basis much more readily available. The contractor may therefore
decide to refer to adjudication early decisions by the architect of
extensions of time which may be awarded before completion and therefore
before the combined effect of all the events can finally be measured.
In this situation a prospective method of delay analysis may well
be appropriate.
The case of Balfour Beatty Construction Ltd v The Mayor and Burgess
of the London Borough of Lambeth29 concerned a challenge
to the enforcement of an adjudicator's decision on the basis that,
in reaching his decision, the adjudicator had failed to act fairly
and had breached the rules of natural justice by preparing his own
collapsed as-built analysis in the absence of one from the referring
party, but had done so without giving the responding party an opportunity
to comment
on the methodology or his approach. In reaching his decision, His
Honour Judge LLoyd Q.C. observed at para.[30] that
''If it [adjudication] is to be utilised effectively, it is essential
that the referring party gives the adjudicator all that is needed
in a highly manageable form. From the material available to me,
it is clear that BB did little or nothing to present its case in
a logical or methodical way. Despite the fact that the dispute concerned
a multi-million pound refurbishment contract, no attempt was made
to provide any critical path. The work itself was no more complex
than many other projects where a CPN [critical path network] is
routinely established and maintained. It seems that BB had not prepared
or maintained a proper programme during the execution of the works.
By now, one would have thought that it was well understood that,
on a contract of this kind, in order to attack, on the facts, a
clause 24 certificate for non-completion (or an extension of time
determined under clause 25), the foundation must be the original
programme (if capable of justification and substantiation to show
its validity and reliability as a contractual starting point) and
its success will similarly depend on the soundness of its revisions
on the occurrence of every event, so as to be able to provide a
satisfactory and convincing demonstration of cause and effect. A
valid critical path (or paths) has to be established both initially
and at every later material point since it (or they) will almost
certainly change. Some means has also to be established for demonstrating
the effect of concurrent or parallel delays or other matters for
which the employer will not be responsible under the contract.''
Contrary to the discussion above about the court's tendency to be
concerned with what actually happened, this appears to be advocating
the time impact analysis methodology, but warns of the need to be
able to justify and validate the original programme and the requirement
of sound revisions to it at the occurrence of each event (requiring
consistent and accurate progress data). This is consistent with the
guidance given in the SCL Protocol,30 which confirms that
the time impact analysis method will not be appropriate if the planned
programme is not sufficiently detailed or has not been regularly updated
with progress data. The above passage does not therefore appear to
rule out any of the other methods of analysis (such as collapsed as-built
or the planned-impacted methods) and provides no assistance as to
how concurrent or parallel delays are to be dealt with.
However, the application of the method of analysis known as time impact
analysis or windows analysis involving the generation of regular updates
to the programme and therefore multiple iterations of the programme
is not without potential difficulty. Some of these difficulties were
highlighted in the recent case of Skanska Construction UK Ltd v
Egger (Barony) Ltd,31 in which His Honour Judge David
Wilcox was not well disposed to the evidence presented by one of the
delay analysis experts who had produced a time impact analysis and
a large report that the judge described as a work of great industry.
It also appears that the expert had made mistakes in the base programme
which he had had to recreate with logic in order to apply the time
impact analysis technique. In the final analysis, Judge Wilcox preferred
what appears to have been the simpler and more factually based approach
of the other expert.
It is clear that, in order to determine whether an event affected
the completion date, it is necessary to determine whether the event
affected the critical path. But a further question is whether the
architect has to make use of critical path analysis to inform his
or her opinion about entitlement or whether he or she can simply form
an impression about what the critical path is at the time of the event.
The extent to which an assessment of delay may be impressionistic
The obligations of the employer's agent when considering the contractor's
entitlement to an extension of time are usually defined in subjective
terms. For example, in the case of the JCT 98 Standard Form, in accordance
with cl.25, if the architect is of the opinion that the event alleged
by the contractor to have caused delay is a relevant event, and that
the completion of the works is likely to be delayed thereby beyond
the completion date, then the architect is required to give such an
extension of time for that event as is fair and reasonable. The process
of forming an opinion and deciding upon what is fair and reasonable
are both subjective requirements that imply the exercise of some degree
of discretion on the part of the architect.
Further, in the authors' view, critical path analysis can only ever
be regarded as a model that approximates the sequence and duration
of the operations and activities on site. The perfect model would
follow each resource around the site and show what it was doing and
in what location and the sequence in which it carried out its work.
Records are invariably not available at this level of detail, and
further analysis at this level may involve tens of thousands of operations,
any meaningful analysis of which would be impossible. Critical path
analysis therefore has, at each level, to be a summation of groups
of like operations. The higher the level of the analysis and the smaller
the number of activities shown on the analysis, the easier it is to
follow and understand but the higher the level of summation and therefore
probably the higher the level of approximation. There is always therefore
likely to be some level of impressionistic assessment applied to decisions
about the extent of extensions of time, even where critical path delay
analyses form the basis of such decisions.
However, in John Barker Construction Ltd v London Portman Hotel
Ltd,32 it was said that, in exercising his duty under
cl.25, the architect, or contract administrator, must undertake a
logical analysis in a methodological manner of the impact of the relevant
events upon the contractor's programme. The application of an impressionistic,
rather than a calculated and rational, assessment is not sufficient.
John Marrin Q.C. has expressed the following view in relation to this
decision:
'' . . . indeed, there are those who'd say that the real point behind
the case is that in practice Mr Recorder Toulson was calling for
all significant extension of time assessments to be done by some
CPM method, which seems to have some difficulties associated with
it.
One point is that there are lots of rather modest disputes in which
the cost of that approach would simply be not worth it.
Secondly, there are several forms of contract which seem to be less
than wholly amenable to such methods. One takes the JCT Standard
Form, they have as I've suggested, in some places built into them,
apparently something in the nature of a discretion on the part of
architect; that is to say that once he's undertaken whatever analysis
and research he needs to get a view of the extensions of time and
the incidence of delay, he then applies what I have called a discretion,
which is no more and no less than asking himself a question, it
is fair and reasonable that there should be an extension of time
in these circumstances? Where you have a contract written in that
way, and there are many of them, it seems that by and large, the
final answer on extension of time is not one which can logically
be developed by the use of computer program software and can only
in the end be resolved by the exercise of some sort of discretion.''
The John Barker case was considered in the recent case of Balfour
Beatty Construction Ltd v The Mayor and Burgess of the London Borough
of Lambeth33 in which, although the point was not decided,
it was contended by the defendant at para.[21] that
''In the context of a dispute about the time for completion a logical
analysis includes the logic required for in the establishment of a
CPN [critical path network]''.
However, the question of what was required of the architect when operating
cl.25 of JCT 1980 was also explored in The Royal Brompton Hospital
NHS Trust v Hammond (No.7).34 This was a case in which it was
alleged that the architect had been negligent in awarding extensions
of time. Judge Seymour stated at para.[32]:
''it was plain from the evidence called at the sub-trial on behalf
of the Claimant, in particular that of Mr. Gibson, who, of course
is a programming expert, that there are a number of established
ways in which a person who wishes to assess whether a particular
event has or has not affected the progress of construction work
can seek to do that. Because the construction of a modern building,
other than one of the most basic type, involves the carrying out
of a series of operations, some of which, possibly, can be undertaken
at the same time as some of the others, but many of which can only
be carried out in a sequence, it may well not be immediately obvious
which operations impact upon which other operations. In order to
make an assessment of whether a particular occurrence has affected
the ultimate completion of the work, rather than just a particular
operation it is desirable to consider what operations, at the time
the event with one is concerned happens, are critical to the forward
progress of the work as a whole. On the evidence of Mr. Gibson and
Mr. Luder the establishment of the critical path of a particular
construction project can itself be a difficult task if one does
not know how the contractor planned the job. Not only that, but
the critical path may well change during the course of the works,
and almost certainly will do if the progress of the works is affected
by some unforeseen event. Mr. Gibson frankly accepted that the various
different methods of making an assessment of the impact of unforeseen
occurrences upon the progress of construction works are likely to
produce different results, perhaps dramatically different results.
He also accepted that the accuracy of any of the methods in common
use critically depends upon the quality of the information upon
which the assessment exercise was based. All of this does, of course,
emphasise the vital point that the duty of a professional man, generally
stated, is not to be right, but to be careful.. . . His conduct
has to be judged having regard to the information available to him,
or which ought to have been available to him, at the time he gave
his advice or made his decision or did whatever else it is that
he did.''
The above passage raises a number of interesting points. The first
is that it is far from clear that a critical path analysis is always
required or merited. In the case of certain types of delay it may
be so plainly obvious that a delaying event has affected the critical
path that provided such an event is properly evidenced and based in
fact and is a relevant event then the contractor will be entitled
to the time. It may well be valid for the architect to form an impression
of the critical path and the effect of a delay on that path without
undertaking his own critical path analysis. In fact it is not practical
to suggest that an architect must carry out a full critical path delay
analysis exercise every time he or she has to consider an extension
of time.
In practice, of course, it is preferable for the contractor to present
some form of critical path, ideally with an as-built programme, so
that there is an indication of which activities drove the completion
date. Further, if the architect's decision is not accepted, then a
third-party tribunal, who has no prior knowledge of the project, has
to be persuaded of the merits of the contractor's claim, generally
through some sort of delay analysis.
The second point is that there are various techniques for the analysis
and presentation of delay claims and it is essential to recognise
that these various methods can produce different results. The authors
would go further and make the point that, in the hands of two different
delay analysts, the same method of analysis will almost certainly
produce different results, because of the many variables and subjectivity
involved in performing such analyses. It may also be the case that
the analysts are not applying precisely the same methodology even
though they may give the same label to the technique which they are
applying. This is also likely to produce different results.
Finally there is an inherent difficulty in asking a third-party tribunal
to make a decision about what is a fair and reasonable extension of
time when that tribunal has not, unlike the architect or engineer,
previously had any involvement in the project. Critical path analysis
is a calculated approach to determining entitlement with reference
to a logic linked model of the operations, their sequence and interrelationships.
It has to be questioned whether such a calculated model can ever truly
determine the subjective question of what is fair and reasonable.
In the authors' view, it often does not. However, the use of such
techniques can greatly assist in providing a better understanding
of the facts and the interrelationship of the various operations or
activities on site, and can greatly assist in determining what was
the critical path and therefore in deciding what on the balance of
probabilities is fair and reasonable.
* Barrister, Atkin Chambers.
** Director, Brewer Consulting (www.brewerconsulting.co.uk).
1 R. A. Palles-Clark, ''The Use of Critical Path Analysis to Prove
Claims for Delay'', Dissertation submitted in part fulfilment of an
MSc degree in Construction Law & Arbitration, King's College London,
September 2003 (© Centre of Construction Law & Management,
Kings College London and Robert A. Palles-Clark, 2003).
2 R. A. Palles-Clark, ''The value of critical path analysis in proving
delay claims'' [2002] Construction Law Review 41-42 (A Supplement
to Civil Engineering Surveyor).
3 R. A. Palles-Clark, ''Problems with using critical path analysis
for proving delay claims'' [2003] Construction Law Review 47-48
(A Supplement to Civil Engineering Surveyor).
4 Delivered by Andrew Burr at the Pickavance Consulting Masterclass
in delay and disruption management on May 21, 2004.
5 R. A. Palles-Clark, n.2 above, at p.41.
6 Stephen Furst, Vivien Ramsey et al., Keating on Building Contracts
(7th ed., Sweet and Maxwell, London, 2001), p.134, para.20-203, in
the commentary by Adrian Williamson.
7 Balfour Beatty v Chestermount Properties (1993) 62 B.L.R.
1.
8 Nicholas J. Carnell, Causation and delay in construction disputes
(Blackwell Science, Oxford, 2000), p.85.
9 n.6 above, at p.248, para.8-31.
10 ibid. at p.245, para.8-22.
11 ibid. at p.248, fn.97.
12 H Fairweather & Co v London Borough of Wandsworth (1987)
39 B.L.R. 106.
13 John Marrin, ''Concurrent Delay'' (2002) 18 Const. L.J. 446 (based
on a paper delivered to the Society of Construction Law in London
on February 5, 2002).
14 Peak Construction (Liverpool) v McKinney Foundations (1970) 1 B.L.R.
111.
15 Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester)
Ltd (1999) 70 Con LR 32.
16 See ibid. at 37, [13].
17 The Royal Brompton Hospital NHS Trust v Frederick Alexander Hammond
(No. 7) (2001) 76 Con. L.R. 148.
18 Motherwell Bridge Construction Ltd v Micafil Vakuumtechnik
(2002) 81 Con L.R. 44.
19 The Society of Construction Law Delay and Disruption Protocol
(The Society of Construction Law, Oxford, 2002), ss.1.4 and 1.10.
20 The Royal Brompton Hospital v Frederick Alexander Hammond,
n.17 above, in which Judge Seymour considered the proper approach
to the assessment of extensions of time particularly at [31], where,
with reference to the Malmaison case, he provided some guidance
on what is meant by concurrency:
''However, it is, I think, necessary to be clear what one means
by events operating concurrently. It does not mean, in my judgment,
a situation in which, work already being delayed, let it be supposed,
because the contractor has had difficulty in obtaining sufficient
labour, an event occurs which is a Relevant Event and which, had
the contractor not been delayed, would have caused him to be delayed,
but which in fact, by reason of the existing delay, made no difference.
In such a situation although there is a Relevant Event,
'the completion of the Works is [not] likely to be delayed thereby
beyond the Completion Date.'
The Relevant Event simply has no effect upon the completion date.
This situation obviously needs to be distinguished from a situation
in which, as it were, the works are proceeding in a regular fashion
and on programme, when two things happen, either of which, had it
happened on its own, would have caused delay, and one is a Relevant
Event, while the other is not. In such circumstances there is a
real concurrency of causes of the delay. It was circumstances such
as these that Dyson J. was concerned with in the passage from his
judgment in Henry Boot Construction (UK) Ltd v Malmaison Hotel
(Manchester) Ltd at paragraph 13 on page 37...''
21 McAlpine Humberoak Ltd v McDermott International Inc (No.2)
(1992) 58 B.L.R. 1 at 25.
22 Ascon Contracting Ltd v Alfred McAlpine Construction Isle of
Man Ltd (1999) 66 Con. L.R. 119.
23 McAlpine Humberoak v McDermott International, n.21 above.
24 ibid. at 26 and 28.
25 Henry Boot Construction Ltd v Malmaison Hotel, n.15 above.
26 Ascon Contracting v Alfred McAlpine Construction Isle of Man,
n.22 above. In this case, Ascon was the reinforced concrete sub-contractor
employed by Alfred McAlpine on a building project near the seafront
on the Isle of Man. Ascon argued that unexpected tidal water ingress
had caused delays to the concrete pours, whereas Alfred McAlpine (by
way of defence) put forward one particularised general allegation
that Ascon had not provided sufficient steel fixers.
27 Henry Boot Construction v Malmaison Hotel, n.15 above.
28 As was the case, for example, in Yorkshire Dale Steamship v
Minister of War Transport [1942] A.C. 691.
29 Balfour Beatty Construction Lid v The Mayor and Burgess of the
London Borough of Lambeth [2002] B.L.R. 288: 84 Con. L.R. 1: [2002]
C.I.L.L. 1873.
30 SCL Protocol, n.19 above, at p.48.
31 [2004] EWHC 1748 (TCC).
32 John Barker Construction Ltd v London Portman Hotel Ltd (1996)
83 B.L.R. 31.
33 Balfour Beatty v London Borough of Lambeth, n.29 above.
34 The Royal Brompton Hospital v Frederick Alexander Hammond,
n.17 above.
- Rob Palles-Clark
Brewer Consulting is an independent practice providing strategic management and commercial consultancy services to the construction, oil and gas, transportation and engineering industries.
The key services we provide are:
Procurement Management
Commercial Management
Dispute Resolution
Training
The breadth of our international experience and network of professional business partners allows us to undertake assignments worldwide. |
London
Tel: +44 (0)20 7389 3800
Epsom
Tel: +44 (0)1372 727100
Northampton
Tel: +44 (0)1604 620404
Stirling
Tel: +44 (0)1786 430800
Abu Dhabi
Tel: +971 (0)2 414 6670
Dubai
Tel: + 971 4 211 5165
admin@brewerconsulting.co.uk |
|