Adjudication was intended by Parliament to be a short and accessible
means of resolving construction contract disputes falling within
the scope of the Housing Grants, Construction and Regeneration Act
1996 ("the Act"). Despite the relative maturity of adjudication,
the tension between the timescale for the adjudicator to reach the
decision1 and the often considerable difficulty of dealing
fairly and appropriately with the issues in dispute is ever present.
Where a referring party refers a large and complex dispute involving
many issues the problem is even greater.
When faced with this situation the adjudicator should ask the parties
for an extension of time appropriate to deal with the adjudication.
The referring party may unilaterally agree to an extension of up
to 14 days beyond the statutory 28 day period for reaching the decision,
but the responding party may not agree to an extension beyond that
period. If this happens, then the adjudicator has to decide between
resigning and attempting to reach a decision in totality or perhaps
on discreet issues.
Alternatively the adjudicator may decide that the referring party
has failed to prove its case. In the authors' experience this appears
to have been used by some adjudicators to avoid digging too deeply
whilst producing a decision. This outcome for a referring party
is of course a disaster, since it is likely to finally determine
the dispute referred and most certainly determines it in the short
term.
The questions we address in this article are:
1. Can the adjudicator actually do this?
2. What can be done to avoid this unwanted outcome?
In other words: "What must a referring party do to prove its
case?
Ascertaining the facts and the law
Adjudication (in accordance with the Act) is a means of resolving
disputes arising under the contract. Most contracts involving construction
works in the UK are governed by the law of England, Scotland or
Ireland. As a general rule therefore the dispute must be decided
with reference to the rights and obligations of the parties to that
contract as governed by the law of that contract.
The Act, at section 108 (2)(f), provides that the contract shall
'enable the adjudicator to ascertain the facts and the law.' This
is therefore a power rather than a duty, and is not therefore mandatory.
With a view to conforming to the provisions of the Act standard
contracts must give effect to this provision.
The various standard adjudication procedures vary as to how this
power is expressed or implemented. JCT at Clause 41A.5.5 of the
Standard Form of Building Contract 1998 provides that: "In
reaching his decision the Adjudicator shall act impartially and
set his own procedure; and at his absolute discretion may take the
initiative in ascertaining the facts and the law as he considers
necessary in respect of the referral ..."
By contrast, the ICE adjudication clauses repeat S108 (2)(f) of
the Act and incorporate the ICE adjudication procedure which at
paragraph 5.5 provides that: "The Adjudicator shall have
complete discretion as to how to conduct the adjudication, and shall
establish the procedure and timetable , subject to any limitation
that there may be in the Contract or the Act. He shall not be required
to observe any rule of evidence, procedure or otherwise of the court.
. . "
Rule 17 of the TeCSA adjudication rules provides that: "Wherever
possible, any decision of the Adjudicator shall reflect the legal
entitlements of the Parties. Where it appears to the Adjudicator
impossible to reach a concluded view upon the legal entitlements
of the parties within the practical constraints of a rapid and economical
adjudication process, any decision will represent his fair and reasonable
view, in the light of the facts and the law insofar as they have
been ascertained by the Adjudicator, of how the disputed matter
should lie unless and until resolved by litigation or arbitration."
The significant differences between these provisions must be reflected
in any observations that we make about the applicability of the rules
of evidence and the proper approach to questions of evidence.
From a practical point of view, the more complex the matter the
less time the adjudicator has to make enquiries of his own into
the matters in dispute. Thus although the adjudicator has the power
(but no obligation) to ascertain the facts and the law often he
does not have the time. The TeCSA procedure quoted above uniquely
seeks to provide the adjudicator with a solution to this dilemma.
However, in our experience, it is uncommon in English contracts
and not incorporated into Scottish and Irish contracts.
Even if incorporated, this approach should not be relied upon by
the referring party. In general, if the case has not been clearly
argued and has limited merit, then a party to an adjudication is
likely to come a cropper if it hopes that the adjudicator will in
some way fix the defects in its case, or give it the benefit of
the doubt, or even provide a decision that reflects a compromise.
There is only one referral (and that must reflect a pre-existing
dispute) but the other party can respond in very wide terms, whether
these have been canvassed previously or not2, and so
the referring party must get its case right from the start.
His Honour Judge Lloyd QC3 has observed that: "If
it [adjudication] is to be utilised effectively, it is essential
that the referring party gives the adjudicator all that is needed
in a highly manageable form.." It is therefore essential
for the parties to set out their respective cases in the clearest
and most accessible way possible, and to assist the adjudicator
with the task of navigating through the issues and the supporting
documents.
If this is not done, then there is the very real risk that some
adjudicators may rather too readily conclude that the referring
party has failed to prove its case, in other words a decision that
the referring party has failed to satisfy the burden of proof. But
is that approach justified?
Evidence and the burden of proof
Evidence is information by which facts tend to be proved and may
take the form of testimony, hearsay evidence, documentary evidence,
real evidence, circumstantial evidence, or opinion evidence.
The burden of proof is the obligation to prove an assertion. There
are two kinds of burden, the legal burden of proof and the evidential
burden of proof. The legal burden of proof is the rule of evidence
whereby a party making an assertion about a fact in issue is under
a duty to prove it in order to succeed. The evidential burden of
proof is the obligation of the party making an assertion to provide
or adduce sufficient evidence of sufficient quality to persuade
the tribunal that their account of the facts is to be preferred.
After both parties have adduced all of their evidence, the tribunal
of fact makes the decision as to whether a party has proved a fact
in issue and therefore satisfied the legal and evidential burdens
of proof.
In deciding upon finding a fact, the tribunal must give weight to
each of the components of the evidence placed before it by the parties
in connection with that fact. In our view that concept applies equally
to adjudication as to more lengthy processes such as arbitration.
The scope for an adjudicator to decide that the burden of proof
has not been met
There is likely to be limited time (although time can be extended
by agreement) for an adjudicator to investigate the matters in dispute.
The approach often adopted by adjudicators is therefore to look
at the evidence of the parties and decide which is to be preferred
in relation to each issue and then adopt that position. This is
a very common approach adopted in relation to the resolution of
disputes about the value of interim payments for example.
If it is clear that the case made is hopeless and the burden of
proof has not been discharged then the adjudicator is entitled to
conclude and indeed should conclude that the burden has not been
satisfied.
It must be borne in mind that the standard of proof is to demonstrate
that on the balance of probabilities the assertion is true (i.e.
more than 50% likely). Thus, if the evidence is very evenly balanced,
then the adjudicator is also entitled to decide that the burden
has not been satisfied.
However, in the recent case of Stephens v Cannon4, the Court
of Appeal was asked to review a lower court decision in relation
to the valuation of a house which had been decided on the basis
of the burden of proof. Mr Justice Wilson analysed a number of cases
from which he drew a series of propositions. One case in point was
the case of Cooper v Floor Cleaning Machines Ltd and Crompton5
. In this case the Court of Appeal found that the lower court had
been wrong to dismiss both the claim and counterclaim for failure
to discharge the burden of proof, and found that the judge erred
in failing to analyse the evidence and that, had he done so, he
would have found that the defendants had discharged the burden of
proof. It was also found that before resorting to dismissal for
want of discharge of the burden of proof, a court should raise with
Counsel the possibility that such a course might have to be taken.
Mr Justice Wilson at paragraph 46, set out 5 propositions, the two
principal ones being as follows:
(a) The situation in which the court finds itself before
it can despatch a disputed issue by resort to the burden of proof
has to be exceptional. . .
(c) The exceptional situation which entitles the court to resort
to the burden of proof is that, notwithstanding that it has striven
to do so, it cannot reasonably make a finding in relation to a disputed
issue. . .
In this case, it appears that the trial judge had not done enough
to evaluate the evidence and had set himself the task of trying
to adopt one or other of the two party's valuations. Justice Wilson
observed at paragraph 49 that "had the master asked himself
not "which of the two valuations should I accept?" but
"what, in the light of the evidence of the two valuers, was
the probable value of the property?" and had he then not merely
noted some of the specific differences between the valuers but sought
to adjudicate in relation to them, he might well, I believe, have
been able to answer it." The appeal was allowed and the
proper valuation referred back to the court.
In summary
There will be circumstances where it is quite appropriate for an
adjudicator to conclude that a party has failed to satisfy the burden
of proof and discharge an issue on that basis. If he does so then,
although he may not be required to give reasons, he probably has
a duty to explain the investigation carried out and why such a decision
has been reached. It is not so clear if the concept of notifying
Counsel (or the parties) prior to dismissal is practical in the
short time scale of adjudication.
We suggest that whilst adjudication generally does not require the
adoption of court procedures and some adjudication procedures may
exclude the requirement to follow the rules of evidence (but do
not prohibit their use), there is a basic obligation on an adjudicator
to do his job. That is to decide the issues referred to him within
the required 28 or 42 day statutory timescale. If he cannot properly
achieve this objective he must resign or seek an extension. What
in the authors' view he should not do is fail to engage with the
case and too readily despatch an issue on the basis of the burden
of proof. Whilst the Stephens v Cannon case underpins this
thinking, adjudication is different to litigation and there is likely
to be limited scope in complex adjudications for investigation of
the facts. However in our view, the adjudicator should always do
his best whilst balancing the investigation against the exigencies
of the timetable and the cost of the adjudication.
1 which must be complied with if the recent Scottish
Inner House Court of Session case of Ritchie Brothers (Pwc) Ltd
v. David Philp (Commercials) Limited [2005] ScotCS CSIH_32 is to
be followed outside Scotland. In this case it was decided that a
decision was invalid if it was delivered even one day late. This
is contrary to a number of earlier Outer House decisions. It is
also contrary to the decision in the English case of Simons Construction
Limited V Aardvark Developments Limited [2003] EWHC 2474 (TCC),
in which Judge Seymour QC decided that an adjudicator's decision
delivered 7 days late was still valid.
2 William Verry (Glazing Systems) v Furlong Homes
Ltd [2005] EWHC 138 (TCC).
3 Balfour Beatty Construction Ltd v The Mayor Burgess
of the London Borough of Lambeth [2002] BLR 288: 84 Con LR1,
at paragraph 30.
4 [2005] EWCA Civ 222.
5 The Times, 24 October 2003.
- Rob Palles-Clark and David Carrick
Brewer Consulting is an independent practice providing strategic management and commercial consultancy services to the construction, oil and gas, transportation and engineering industries.
The key services we provide are:
Procurement Management
Commercial Management
Dispute Resolution
Training
The breadth of our international experience and network of professional business partners allows us to undertake assignments worldwide. |
London
Tel: +44 (0)20 7389 3800
Epsom
Tel: +44 (0)1372 727100
Northampton
Tel: +44 (0)1604 620404
Stirling
Tel: +44 (0)1786 430800
Abu Dhabi
Tel: +971 (0)2 414 6670
Dubai
Tel: + 971 4 211 5165
admin@brewerconsulting.co.uk |
|