What happened to arbitration?

Date 12 July 2006
Judgment The Council of the City of Plymouth v D R Jones (Yeovil) Ltd, (TCC) 31 October 2005
table
The Issue When leave might be granted to appeal against the award of an arbitrator.
table
Implication Leave to appeal against the award of an arbitrator is sparingly given, and parties should consider whether this restriction is acceptable to them prior to entering into an arbitration agreement.





print

Once upon a time, not so long ago, arbitration was the only means of dispute resolution provided for in most standard forms of construction contract, meaning that if the parties had a dispute which they were unable to resolve between themselves then it was necessary to refer those disputes to an arbitrator.  The perceived advantages of arbitration were well known and included its privacy and the flexibility it offered to devise a procedure that was best suited to any particular dispute.  This last feature also offered the opportunity to limit costs and timescales.

Against these advantages can be set a number of disadvantages, including arbitration’s relative inflexibility in being able to accommodate disputes involving more than two parties.

Over recent years standard forms of construction contract have started to include provision for other forms of dispute resolution.  Most notably this has been because of the requirements of the Housing Grants, Construction and Regeneration Act 1996 for a compliant adjudication procedure, but there has also been recognition of the fact that other forms of alternative dispute resolution may sometimes be appropriate.  For example, provision for mediation appears in the most recent editions of the JCT forms.

Together with these new options for resolving disputes there has been a general trend away from arbitration, preferring instead to rely upon the courts to provide a final resolution to any disputes that may arise.  The clearest example of this is found in the JCT suite of contracts where, from a situation where once only arbitration was envisaged, they started (from 1998) to offer litigation as an option which the parties could select should they wish.  Currently the 2005 editions generally present litigation as the norm, with arbitration being relegated to an option for the parties to select should they wish.  The exception to this is the JCT Major Project Construction Contract and its associated subcontract, which does not even offer arbitration as an option.

It is interesting to speculate why this fundamental change of position has occurred, but it is likely to have been influenced by the fact that arbitration is no longer generally perceived as either quicker or cheaper than litigation, whilst many of the disputes which are likely to be referred to arbitration or litigation will already have been the subject of adjudication.

One feature of arbitration which may rank as both an advantage and a disadvantage concerns the ability to appeal against an arbitrator’s award.

Section 69 of the Arbitration Act 1996 provides that any appeal to the courts from the award of an arbitrator can only be made in respect of a question of law, meaning that the arbitrator’s award cannot be challenged in respect of any findings of fact.  Even if one of the parties wishes to appeal on the basis of a question of law that is only possible if either the other party agrees, or the court gives leave to appeal.  Leave to appeal will only be granted if all of the criteria set out in section 69(3) of the Act are met. One of the criteria is that, on the basis of the findings of fact, the award must either be obviously wrong or the question of law which is raised is of general public importance and the decision of the tribunal is at least open to serious doubt. 

These restrictions on appeals are seen by many as being a positive advantage of arbitration, in promoting certainty and making it difficult for any award to be challenged in the courts.  Of course, if you are unhappy with an award, your views of this feature of arbitration may be different.

A good example of the difficulties parties face in bringing an appeal against an arbitrator’s award can be seen from the case of City of Plymouth v D R Jones (Yeovil) Ltd.  Here the arbitrator had given an award dealing with when and how a contract had come into existence, identifying the relevant documents and terms and declining the council’s application for the contract to be rectified.  

The council sought leave to appeal this decision on a question of law and the Judge clearly identified the two main difficulties with the council’s application. 

The first difficulty faced was that many of the decisions which it now sought to challenge seemed to be primarily questions of fact (e.g. when the contract came into existence), rather than questions of law.  In previous cases, Judges have commented adversely upon a trend to attempt to put forward findings of fact as questions of law so that they may be appealed and, as in the previous cases, the Judge was not convinced.

The second difficulty which faced the council was that as the award related only to a particular set of facts and a particular project, it could not be said that any point of law which might be identified was of general public importance.  The consequence of this was that for leave to be granted the Council had to show that the decision was obviously wrong.  In relation to important matters the Judge in this instance did not even consider the decision to be arguably wrong, and went so far as to suggest that it was probably correct.

In the light of these conclusions it is perhaps unsurprising that the Judge stated that it was “… an application which never had any prospect of success”.  All those who enter into construction contracts should bear this decision in mind in deciding what value they place upon the final nature of an arbitrator’s award, and whether they wish to incorporate an arbitration provision.

- Owen Fox
CJ-0627

Brewer Consulting is an independent practice providing strategic management and commercial consultancy services to the construction, oil and gas, transportation and engineering industries.

The key services we provide are:
Procurement Management Commercial Management Dispute Resolution Training
The breadth of our international experience and network of professional business partners allows us to undertake assignments worldwide.
London
Tel: +44 (0)20 7389 3800

Epsom
Tel: +44 (0)1372 727100

Northampton
Tel: +44 (0)1604 620404

Stirling
Tel: +44 (0)1786 430800

Abu Dhabi
Tel: +971 (0)2 414 6670

Dubai
Tel: + 971 4 211 5165

admin@brewerconsulting.co.uk
© Brewer Consulting