Construction and engineering projects
can occasionally give rise to complex multi party disputes. Where
separate dispute resolution proceedings have to be conducted between
individual parties to a project, this can give rise to excessive costs
and inconsistent findings. It is for this reason that many of the
standard forms of construction contract attempt to allow joint arbitration
proceedings where the disputed issues between three or more parties
have a measure of commonality.
Typically however, these arrangements are very difficult to operate
in practice. Indeed the attempts of the civil engineering industry
to bring employer, main contractor and sub-contractor disputes together
was examined by the House of Lords in 2000 in the case of Lafarge
Redlands Aggregates v Shepherd Hill Civil Engineering. It was held
that, despite the wording of the contracts, a sub-contractor would
be free to commence its own separate arbitration with the main contractor,
without being forced to join the employer into the proceedings, if
the main contractor did not progress with reasonable speed the dispute
resolution mechanisms under the main contract.
A rather different situation was examined more recently in the case
of City & General (Holborn) v AYH where the court had to consider
the appointment of a single arbitrator to deal with related disputes
arising both under the main contract and arising under the professional
appointments of the project manager and quantity surveyor.
City & General had contracted with Kier to carry out refurbishment
works at the site of the former Patent Office Library in London. The
contract was in the JCT Standard Form with some contractor design
for a contract sum of approximately £12 million. City &
General had also engaged AYH to act both as project manager and quantity
surveyor for the development under two separate deeds of appointment.
Unfortunately the project did not proceed smoothly. Completion was
not achieved until 80 weeks after the due date. Kier was granted substantial
extensions of time and the cost of the works escalated to the extent
that Kier had been paid some £18.5 million but was claiming
a further £11 million.
These matters became the subject of disputes between the parties.
Some of these disputes had been addressed in three adjudications between
Kier and City & General. In due course, however, City & General
issued a notice of arbitration against Kier encompassing the entire
range of disputes between the parties under the contract, including
the value of the works, entitlement to extensions of time, loss and
expense and delay damages. An arbitrator was duly appointed to decide
those matters.
Prior to commencing arbitration with Kier, City & General had
also written to AYH setting out its view that AYH had failed to exercise
all the reasonable skill, care and diligence to be expected of a qualified
quantity surveyor and project manager. Referring to clause 17.2 of
AYH's deed of appointment, City & General notified AYH that the
disputes between them should be referred to the same arbitrator as
had been appointed in the arbitration with Kier.
Clause 17.2 provided that "if the dispute to be referred to arbitration
under this deed raises issues which are substantially the same as,
or are connected with issues raised in related disputes . . . the
dispute under this deed shall be referred to the arbitrator appointed
to determine the related dispute". This provision was based upon
clause 41 of the JCT 1980 standard form.
AYH challenged City & General's rights to bring about an arbitration
in this manner, and the matter came before Mr Justice Jackson in the
Technology and Construction Court. AYH contended that certain of the
complaints raised by City & General were not caught within the
arbitration clause of their deeds of appointment and more significantly,
that there was an insufficient convergence of issues in the two arbitrations
to allow clause 17.2 to be triggered.
Justice Jackson concluded that it would not be necessary for every
single issue in dispute with AYH to be substantially the same or connected
with an issue in the dispute with Kier. The real question was what
proportion of the issues in the two arbitrations must converge in
order to trigger clause 17.2.
To answer this it was proper to have regard to the commercial purpose
of the contract clause. This was to avoid a multiplicity of proceedings
which would generate excessive costs and carry the risk of inconsistent
findings. With this in mind the threshold of clause 17.2 should not
be set too high. It was not necessary that the majority of issues
in dispute with AYH should be the same or connected with the issues
in dispute with Kier. It would be sufficient if a material portion
of the issues were the same.
Since it was clear that a material portion of the issues in the arbitration
against AYH were substantially the same as or connected with the issues
in the arbitration with Kier, clause 17.2 was triggered. In consequence
the court appointed the arbitrator who was already engaged to deal
with the Kier dispute as arbitrator in the proceedings between City
& General and AYH.
- Geoff Brewer
Brewer Consulting is an independent practice providing strategic management and commercial consultancy services to the construction, oil and gas, transportation and engineering industries.
The key services we provide are:
Procurement Management
Commercial Management
Dispute Resolution
Training
The breadth of our international experience and network of professional business partners allows us to undertake assignments worldwide. |
London
Tel: +44 (0)20 7389 3800
Epsom
Tel: +44 (0)1372 727100
Northampton
Tel: +44 (0)1604 620404
Stirling
Tel: +44 (0)1786 430800
Abu Dhabi
Tel: +971 (0)2 414 6670
Dubai
Tel: + 971 4 211 5165
admin@brewerconsulting.co.uk |
|