In the recent case of Shawton Engineering
v DGP International, the Court of Appeal had to examine the circumstances
in which a contracting party might lawfully terminate a contract on
the basis of delay in performance by the other party, when that party's
obligation is to complete the work within a reasonable time.
British Nuclear Fuels had a contract with Kvaerner Construction to
construct facilities at Sellafield for handling nuclear waste. Kvaerner
subcontracted this work to a joint venture called KAT Nuclear. KAT
were effectively the main contractor and they placed a subcontract
with Shawton for the design and manufacture of a number of work packages.
Shawton in turn subcontracted the design work for five of those packages
to DGP.
Disputes arose between Shawton and DGP concerning delay in producing
the designs. There had been a number of variations to the work to
be carried out by DGP and although there was no contractual mechanism
for extending the time on account of these variations, Shawton was
prepared to give DGP substantially more time in which to complete
the work. A series of revised programmes was accepted, and the parties
entered into an agreement extending the time for completion of the
design work and agreeing that Shawton would pay for the variations
claimed by DGP. It seems that underlying this agreement was the fact
that further up the line, KAT were themselves having difficulties
and were not pressing Shawton to deliver the plant and equipment on
time. There was apparently no operational need for the deliveries.
Despite this, eventually these matters came to a head and Shawton
issued a letter purporting to terminate DGP's subcontract. Shawton
claimed the cost of another design subcontractor in the amount of
approximately £820,000, a sum which was more than three times
DGP's original contract price. Shawton also claimed approximately
£1m for alleged delay and disruption.
When these matters came to court, Shawton said that DGP had been in
breach of its obligation to complete and this entitled Shawton to
terminate the subcontract. Shawton accepted that where the contract
did not provide a mechanism for extending the time for completion,
the legal effect of the variations to the work was that DGP became
entitled to complete their work within a reasonable time. Put another
way, time was "at large".
On hearing these matters in the Technology and Construction Court,
Judge Gilliland QC noted that it was for Shawton to prove on the balance
of probabilities that DGP had failed to complete its work within a
reasonable time. Judge Gilliland had certain views about how this
should be approached. Firstly, he rejected Shawton's submission that
the reasonable time should be ascertained by reference to the original
contract period extended only by an agreed period for variations.
Even where the experts appointed by the parties had agreed an appropriate
extension of time for the variation works, this, together with the
originally agreed period, could not be regarded as a fair indication
of what was a reasonable time for completion of the work. This was
in effect to treat the originally agreed period as being a reasonable
period.
In the present case, it was clear that DGP had seriously underestimated
the number of drawings which would be required and how long the work
would take. Judge Gilliland considered that the approach contended
for by Shawton might be correct for a contract with express provisions
for an extension of time, but not where time had become "at large".
Judge Gilliland also had a particular view concerning to the effect
of instructing variations after the original completion date. He held
that by instructing extra work after the agreed or extended completion
dates, Shawton in effect started time running afresh. DGP became entitled
to a reasonable time judged objectively for carrying out the remainder
of its work.
Lord Justice May, sitting in the Court of Appeal, appeared to be rather
unimpressed by the approach taken by Judge Gilliland on these points.
If DGP had initially underestimated the time required to complete
its works, Shawton would have had the contractual benefit of that
underestimation, and this could not be entirely ignored simply because
DGP's obligation became to complete within a reasonable time.
Lord Justice May was similarly not persuaded by the argument that
instructing a variation after the original completion date meant,
by itself, that the reasonable time had to be assessed afresh.
Despite these criticisms, Lord Justice May agreed that in circumstances
where the obligation was to complete within a reasonable time, Shawton
could only in law legitimately terminate the contract for delay if
either it had given reasonable notice making time of the essence,
or DGP's failure to complete within a reasonable time amounted to
a fundamental breach depriving Shawton of substantially the whole
benefit of the contract.
Having reviewed the evidence Lord Justice May agreed with Judge Gilliland
in holding that Shawton had not made time of the essence when it had
obtained revised programmes which DGP had indicated it would "try"
to meet. Accordingly, DGP's obligation had remained to complete the
works within a reasonable time. Against that background, and where
on the evidence DGP had been making an effort to complete the contract
works, it would always be difficult for Shawton to prove that DGP
were in repudiatory breach.
In consequence, the court was correct to conclude that Shawton had
unlawfully terminated the subcontract and its appeal against that
finding was dismissed.
- Geoff Brewer
Brewer Consulting is an independent practice providing strategic management and commercial consultancy services to the construction, oil and gas, transportation and engineering industries.
The key services we provide are:
Procurement Management
Commercial Management
Dispute Resolution
Training
The breadth of our international experience and network of professional business partners allows us to undertake assignments worldwide. |
London
Tel: +44 (0)20 7389 3800
Epsom
Tel: +44 (0)1372 727100
Northampton
Tel: +44 (0)1604 620404
Stirling
Tel: +44 (0)1786 430800
Abu Dhabi
Tel: +971 (0)2 414 6670
Dubai
Tel: + 971 4 211 5165
admin@brewerconsulting.co.uk |
|