The recent case of Machenair v Gill
and Wilkinson examined the manner in which a contractor's standard
conditions may be incorporated into a subcontract by simple reference
to those conditions on the face of the order issued to the subcontractor.
Gill was engaged as subcontractor for the design, supply and installation
of mechanical and electrical installations for the refurbishment of
Macaulay Hall at Leeds Metropolitan University. Gill had engaged Machenair
as sub-subcontractor to carry out the mechanical works on the project.
The sub-subcontract was based upon three separate purchase orders
which in large measure engaged Machenair only for the provision of
labour.
Disputes arose between the parties concerning the value of the final
account. The parties could not agree upon the causes of delay to the
installation of the mechanical works and whether Gill was entitled
to deduct damages for delay. Machenair also claimed an entitlement
to be paid for additional resources brought to site.
When these matters came before the court, it became necessary to determine
what were the terms of the sub-subcontract between Gill and Machenair.
Each of the three purchase orders sent by Gill to Machenair had a
note at the bottom stating "this order is placed subject to our
conditions of purchase, a copy which is available upon request".
Gill contended that this note had the effect of incorporating its
standard conditions into the subcontract. Machenair disputed that
position.
Under English law, it is an accepted principle that express terms
can be incorporated in a contract simply by making a reference to
those terms within the written order, but without setting out in full
all the relevant terms. For this to be effective it is essential that
the party tendering the document has done all that has reasonably
sufficient to give the other party notice of the terms. If this should
be disputed, it is then for a court or tribunal as a matter of law
to decide whether there is evidence for holding that the notice given
was reasonably sufficient. There have however been a long line of
cases in which the notice given of terms to be incorporated into a
contract has been held to be insufficient.
In the 1972 case of White v Blackmoor the conditions were printed
on the back of an order document without any adequate reference on
the face of the document. The court rejected the submission that the
conditions should be incorporated into the contract. In the 1996 case
of Poseidon Freight Forwarding v Davis Turner, contract documents
had been sent by fax with reference made to conditions stated to be
on the back, but those conditions were not in fact contained on the
back or otherwise communicated. Again the court rejected the application
of the disputed contract conditions. In Richardson v Rowntree the
court refused the incorporation of conditions which had been obliterated
by a printed stamp.
Although a party receiving a contract document may know that it contains
reference to additional conditions, if a particular condition relied
upon by the other party is one which is onerous or unusual, or one
which seeks to exclude a right which would otherwise be given by statute,
very clear notification of the term must be given. In the 1956 case
of Spurling v Bradshaw Lord Denning said "Some clauses which
I have seen would need to be printed in red ink on the face of the
document with a red hand pointing to it before the notice could be
held to be sufficient".
Returning to the present case, Mr Justice Jackson concluded that Gill's
standard conditions were not incorporated into the sub-subcontract.
On the first two purchase orders, the crucial words mentioning that
the order was placed subject to Gill's conditions of purchase had
been substantially obliterated by the fax header to such an extent
that it was unreasonable to expect Machenair to decipher the words
underneath.
Justice Jackson commented that even if that had not been the case,
the words used at the bottom of the purchase orders were not sufficient
to incorporate Gill's standard conditions. Those conditions were extensive.
They were not one of the standard forms used within the construction
industry and they had never been supplied to Machenair. The note on
the purchase orders did not contain any form of resume of the conditions.
Taking all those points into account it was not reasonable to impose
those conditions upon Machenair.
- Geoff Brewer
Brewer Consulting is an independent practice providing strategic management and commercial consultancy services to the construction, oil and gas, transportation and engineering industries.
The key services we provide are:
Procurement Management
Commercial Management
Dispute Resolution
Training
The breadth of our international experience and network of professional business partners allows us to undertake assignments worldwide. |
London
Tel: +44 (0)20 7389 3800
Epsom
Tel: +44 (0)1372 727100
Northampton
Tel: +44 (0)1604 620404
Stirling
Tel: +44 (0)1786 430800
Abu Dhabi
Tel: +971 (0)2 414 6670
Dubai
Tel: + 971 4 211 5165
admin@brewerconsulting.co.uk |
|