In October 1999 Haden Drysys entered into a contract with Decoma
to design, construct, install and commission a "turnkey"
paint finishing system to be installed at Decoma's facility at Halewood
on Merseyside. The contract value was approximately £8.75
million. The contract was a bespoke one specifically negotiated
between the parties, but in many respects incorporated familiar
terms for contracts of this type. The contractor undertook to complete
the works in a timely, efficient and workmanlike manner and to do
everything necessary for the proper execution and completion of
the works in conformity with all relevant standards and the equipment
performance specifications contained within the contract.
Under Article 11 of the contract the contractor warranted that upon
final completion, the material and equipment supplied and installed
by him would operate in accordance with the equipment performance
specifications. Article 12 of the contract provided for liquidated
and ascertained damages. Such damages were payable if Haden failed
to achieve the final completion date and the sum ascended on a rising
scale to a maximum amount of 5% of the contract price.
The paint finishing system had been taken over and operated by Decoma
for some years before complaints concerning Haden's performance
came to court in proceedings where Decoma claimed sums in excess
of £18 million from Haden. The court was asked to accept certain
assumptions concerning Haden's performance in order to examine the
relevant contract provisions in a series of preliminary issues.
Those included that Haden had had considerable difficulty with the
installation of the plant and equipment and had been unable to install
all of the equipment in accordance with the specification so that
performance testing was never completed and thus the final acceptance
test was never satisfied.
In answer to the claims made by Decoma, Haden argued that it was
entitled to rely on the conditions of contract in various ways in
order to limit or exclude its liability for damages. If Haden's
contentions were correct, Decoma's entitlement to recovery would
be severely restricted, in all probability to just 5% of the original
contract price.
Central to the analysis of the contract was that in common with
many contracts of this type, the contract differentiated between
the parties' rights and liabilities prior to Final Acceptance and
after Final Acceptance of the spray painting system.
Prior to Final Acceptance, Haden were bound to complete the paint
spraying system such that it passed a Final Acceptance Test by the
relevant contractual date for completion. If Haden failed to meet
this primary obligation in the period prior to Final Acceptance,
Decoma's principal claim would be for liquidated damages as a consequence
of Haden's delay in completing the system to the contractual standards.
This was capped at 5% of the contract price. Of course the delays
might have been so extensive that Decoma's claims for loss of profit
or loss of use would be greater than the liquidated damages capped
at a maximum of 5%. However that possibility was plainly in the
contemplation of the parties at the time they had agreed to the
terms of the contract. The cap was simply a part of the general
allocation of commercial risk between the parties.
The difficulty in this present case was that the delays in completion
of the paint spraying system were assumed to be the result of a
deep rooted failure on the part of Haden to comply with the various
technical requirements. Decoma argued that the contract should be
interpreted on a presumption that a party could not take advantage
of its own wrong. It argued that the parties did not imagine the
situation where the paint spraying system would not have achieved
Final Acceptance so long after the Final Completion date and therefore
it was unfair as a matter of principle to apply contractual provisions
which limited the damages applicable.
His Honour Judge Peter Coulson was unconvinced by such argument.
He commented that "cap" clauses which are a common feature
of commercial contracts, reflect an agreement between the parties
that, in the event of a breach, the wrongdoer's liability will be
fixed at a preset maximum level. In one sense of course, the wrongdoer
who seeks to rely on such a clause is seeking to take advantage
of his own wrong because the cap clause in question can only be
triggered by his breach of contract in the first place. However,
in Judge Coulson's opinion it would be absurd to suggest that if
the capped clause was clear, the wrongdoer could not rely on such
a provision to limit his liability.
Judge Coulson was satisfied that prior to Final Acceptance, Decoma's
claims were limited to liquidated damages and subject to the capped
5%. This entitlement was an exclusive remedy for all claims arising
out of Decoma's inability to use and make a profit out of the paint
spraying system. If there had been a dispute as to whether or not
Haden were complying with the contract terms, Decoma could have
terminated the contract. The reasons for the delay and the nature
and extent of Haden's breaches of contract which may have caused
the failure to achieve Final Acceptance were irrelevant to the proper
construction of the contract. The warranties given by Haden in respect
of the proper functioning of the plant only took effect once Final
Acceptance had been achieved, and thus Decoma's claims were limited
to 5% of the contract price.
- Geoff Brewer
Brewer Consulting is an independent practice providing strategic management and commercial consultancy services to the construction, oil and gas, transportation and engineering industries.
The key services we provide are:
Procurement Management
Commercial Management
Dispute Resolution
Training
The breadth of our international experience and network of professional business partners allows us to undertake assignments worldwide. |
London
Tel: +44 (0)20 7389 3800
Epsom
Tel: +44 (0)1372 727100
Northampton
Tel: +44 (0)1604 620404
Stirling
Tel: +44 (0)1786 430800
Abu Dhabi
Tel: +971 (0)2 414 6670
Dubai
Tel: + 971 4 211 5165
admin@brewerconsulting.co.uk |
|