The term 'cause of action' broadly
refers to the right of a party to bring legal proceedings, for example
to be paid monies due under a contract. The date of accrual of the
cause of action for sums due under a contract will usually depend
upon the terms of the contract itself. However, the starting point
for any consideration of this question is the established principle
that, in the absence of any contractual provision to the contrary,
a cause of action for payment for work performed or services provided
will accrue when that work or those services have been performed or
provided. In such circumstances, the cause of action does not depend
on the making of a claim for payment by the party who has provided
the work or services.
Establishing the date of accrual of the cause of action can often
be critical to the bringing of a claim. The Limitation Act provides
that the period of limitation for bringing claims for breach of contract
will begin from the date of the accrual of the cause of action. If
that date is established by a certificate of practical completion
for the construction works, then there may be little room for doubt
as to the expiry of the period of limitation. Frequently however,
the matter is more complex and an example of the difficulties that
can arise is given by the recent Court of Appeal decision in the case
of Birse Construction v McCormick (UK).
Birse had entered into a contract with McCormick in September 1995
to construct a facilities consolidation project at McCormick's premises
in Haddenham in Buckinghamshire. The bulk of the work had been completed
by November 1996 and as a result, on 15 November of that year, Birse
was able to settle its claim for the direct costs of all changes to
the work in an agreed sum of approximately £1 million.
The previous day, on 14 November 1996, Birse had made a formal claim
for additional site establishment costs to reflect the delay and disruption
to the work and its additional time on site. This claim document,
which was expressly excluded from the settlement agreement, relied
upon 29 separate events which had occurred between November 1995 and
November 1996. In April 1997, Birse submitted a further claim document
which still had at its heart the same 29 events, although the sums
claimed had been significantly reduced.
Little then happened until May 2003, when Birse commenced proceedings
against McCormick. It was therefore recognised that any cause of action
which accrued before May 1997 would be statute barred, there being
an effective limitation period of six years. McCormick immediately
applied for a ruling from the court that Birse's claims were statute
barred and this was heard as a preliminary issue in the Technology
and Construction Court.
In accordance with the contract between the parties, Birse was entitled
to be paid a series of lump sums for carrying out the work according
to a Milestone Payment Schedule. Changes to the amounts payable under
the Milestone Payment Schedule would only come about under the terms
of the contract if there was a work order which had been authorised
by the management contractor acting on behalf of McCormick. This equally
applied to any claims for increase in the lump sum for site establishment
charges. The contract also provided for a final payment process, which
allowed for the administrative completion of the contract including
the final payment of retention monies once the management contractor
had issued a notice of acceptance of the work and Birse had issued
a certificate to the effect that it had no further claims under the
contract.
Birse relied upon this latter contract provision. It argued that its
claims were not time barred on the basis that it had only one cause
of action in respect of its disputed claims. This did not accrue until
final payment, because that was the first occasion on which the management
contractor's decision on the claims was not to be regarded as a temporary
position.
Judge Peter Coulson rejected this argument. He held that the final
payment provisions of the contract made no reference either to reviewing
previous claims or to renewing or formalising previous claims made
by the contractor. The contract worked on the basis of a formal mechanism
for payment of the lump sum contract price and any changes to that
lump sum, including any additional site establishment costs. In the
event of a dispute as to those amounts, there was a formal contract
procedure for the resolution of those disputes. That being the case,
Birse's cause of action accrued when the dispute first arose in connection
with its claims for site establishment costs.
In the Court of Appeal, Lord Justice Clarke agreed with those conclusions.
There was nothing in the words of the clause dealing with final payment
which supported Birse's contention that at that stage, and not before,
the cause of action accrued in respect of the claims being advanced
by Birse for site management charges.
In consequence, Birse's appeal was dismissed.
- Geoff Brewer
Brewer Consulting is an independent practice providing strategic management and commercial consultancy services to the construction, oil and gas, transportation and engineering industries.
The key services we provide are:
Procurement Management
Commercial Management
Dispute Resolution
Training
The breadth of our international experience and network of professional business partners allows us to undertake assignments worldwide. |
London
Tel: +44 (0)20 7389 3800
Epsom
Tel: +44 (0)1372 727100
Northampton
Tel: +44 (0)1604 620404
Stirling
Tel: +44 (0)1786 430800
Abu Dhabi
Tel: +971 (0)2 414 6670
Dubai
Tel: + 971 4 211 5165
admin@brewerconsulting.co.uk |
|