The recent case of Bryen & Langley
v Martin Boston related to the conversion of two flats in London owned
by a Mr & Mrs Boston. Mr Boston engaged a firm of quantity surveyors
to prepare bills of quantities to be sent out to potential contractors.
The preliminaries section of the bills consisted of a list of project
particulars and under the heading of "The Contract" provided
that the 'JCT Standard Form of Building Contract, 1998 Edition, Private
with Quantities' would apply, subject to certain listed amendments.
The stipulated amendments made it clear that Article 5 was to be left
undeleted. Article 5 of the JCT form provides that "If any dispute
or difference arises under this Contract either party may refer it
to adjudication in accordance with clause 41A". Clause 41A sets
out the conditions under which disputes or differences can be referred
to an adjudicator.
Six builders tendered for the works and Bryen & Langley's tender
was the lowest. Negotiations about the price and the works took place
and these eventually led to the agreement of a revised price. Boston's
quantity surveyors wrote to Bryen & Langley confirming Boston's
intention to proceed with the works and confirming that a contract,
in the JCT form, would be issued shortly. The letter also noted that
the cost of levelling floors and a bonus scheme were still to be agreed.
Shortly after that letter Boston's quantity surveyors issued completed
contract documents to Bryen & Langley incorporating the JCT form.
Bryen & Langley duly signed the contract and returned these to
Boston for his signature. Boston never signed the contract.
Meanwhile the works were progressing, and in the event the project
overran and a dispute materialised over the final certificate issued
by the Architect which Boston refused to pay. Bryen & Langley
referred the matter to adjudication under Article 5 asking the adjudicator
to rule upon its claim that Boston was liable to pay it £65,995
due under the Architect's final certificate.
Boston's position was clear from the start. He claimed that because
the works related to a dwelling in which Boston was a residential
occupier, statutory adjudication under the 1996 Construction Act did
not apply. He also claimed that the contract had not incorporated
the JCT form and as such Bryen & Langley had no contractual right
to adjudicate Bryen & Langley disputed these jurisdictional challenges
asserting that even though Boston had never signed his copy of the
contract, all the parties had acted as if a contract in the JCT form
was in place.
The adjudicator ruled in Bryen & Langley's favour on these points
of jurisdiction and allowed the adjudication to proceed. He went onto
award Bryen & Langley the sums contained within the Architect's
certificate.
Boston refused to comply with the award and Bryen & Langley sought
enforcement proceedings in the court. The matter was brought before
HHJ Seymour QC for summary judgment. Boston repeated his view that
the contract did not incorporate the JCT terms and even if it did,
then it was unenforceable under the Unfair Terms in Consumer Contract
Regulations 1999. On the first issue the Judge held that, contrary
to the adjudicator's finding, the JCT form was not incorporated into
the building contract. Accordingly, there was no basis for adjudication.
Bryen & Langley's application for enforcement of the adjudicator's
decision was dismissed. The Judge also rejected Boston's argument
concerning the 1999 Unfair Terms regulations.
Bryen & Langley appealed the decision to the Court of Appeal where
Mr Justice Rimer accepted Bryen & Langley's submission that all
the terms of the building contract were in fact agreed. He commented
that the mere fact that two parties propose that their agreement should
be contained in a formal contract to be drawn up and signed in the
future did not preclude the conclusion that they had already informally
contractually committed themselves on exactly the same terms.
He also agreed with Bryen & Langley that the outstanding issues
of floor levelling and bonus could not be regarded as essential elements
of the building contract that still remained to be agreed. They were
simply variations to be negotiated under the terms of the contract.
In respect of the alternative case under the 1999 Regulations, Justice
Rimer rejected Boston's submission that the adjudication provisions
were contrary to the requirement of good faith and caused a significant
imbalance in the parties' rights. The adjudication provisions were
not imposed by Bryen & Langley (the supplier). It was in fact
Boston (the consumer), acting through his quantity surveyor, who had
imposed them on the supplier by virtue of the original invitation
to tender. In conclusion, Mr Justice Rimer stated that "I regard
the suggestion that there was any lack of good faith or fair dealing
by Bryen & Langley with regard to the ultimate incorporation of
those terms into the contract as repugnant to common sense".
Finding that there was no lack of openness, fair dealing or good faith
he rejected Boston's alternative claim.
Lord Justice Clarke and Lord Justice Pill agreed with the conclusions
of Justice Rimer and the decision of the Adjudicator was duly enforced.
- Geoff Brewer
Brewer Consulting is an independent practice providing strategic management and commercial consultancy services to the construction, oil and gas, transportation and engineering industries.
The key services we provide are:
Procurement Management
Commercial Management
Dispute Resolution
Training
The breadth of our international experience and network of professional business partners allows us to undertake assignments worldwide. |
London
Tel: +44 (0)20 7389 3800
Epsom
Tel: +44 (0)1372 727100
Northampton
Tel: +44 (0)1604 620404
Stirling
Tel: +44 (0)1786 430800
Abu Dhabi
Tel: +971 (0)2 414 6670
Dubai
Tel: + 971 4 211 5165
admin@brewerconsulting.co.uk |
|