Neither the 1996 Construction Act
nor the Scheme for Construction Contracts, which contains model terms
for adjudication, provide for the payment of the costs incurred by
either party in prosecuting or defending claims made in adjudication.
Parliament clearly did not think it essential for adjudication agreements
to provide for the recovery of the parties' costs. Nevertheless, since
the statute is silent upon the matter, it remains open to the parties
to agree within their contract that in the event of adjudication,
the adjudicator will have the power to decide who should pay the parties'
costs.
Despite this, few of the standard forms of construction contract empower
the adjudicator to deal with the parties' adjudication costs. It is
in the non-standard amendments to contracts that reference to the
parties' adjudication costs is frequently found. Indeed, these clauses
often go further than a simple provision that the adjudicator shall
have a discretion to decide who should pay the parties' costs and
provide, for example, that the referring party must pay the costs
of the adjudication, win or lose. Such clauses are currently the subject
of consultation with the Government and it is likely they will eventually
be outlawed.
The recent case of John Roberts Architects v Parkcare Homes examined
the situation where the referring party had discontinued the adjudication
proceedings and in consequence the respondent claimed its abortive
costs in defending the case made against it in the adjudication.
Roberts had been engaged by Parkcare to provide architectural services
in connection with building works to be carried out at their premises
in Salford. The contract between the parties was based upon the RIBA
Conditions of Engagement for the Appointment of an Architect. These
conditions provided for adjudication, but clause 29 had been amended
to the effect that "the adjudicator may in his discretion direct
the payment of legal costs and expenses of one party by another as
part of his decision".
Disputes arose between the parties and on 11 May 2004, Parkcare sent
a letter to Roberts claiming a sum in excess of £1.3 million
in respect of alleged failings in the standard of service provided
by Roberts. The letter required a response within seven days failing
which the matter would be referred to adjudication. Over the next
three weeks Parkcare made two attempts to commence adjudication. On
both occasions Parkcare was forced to accept the point that the adjudicator
did not have jurisdiction since a dispute had not yet arisen. The
adjudications were discontinued and the adjudicator invited to submit
his account to Parkcare for time expended on the matter which Parkcare
paid.
This however was not the end of the matter as far as Roberts were
concerned. They had expended some £87,000 in dealing with the
aborted adjudication and unsurprisingly asked the adjudicator to direct
that Parkcare should pay those costs. In addition, Roberts asked the
adjudicator for a formal order that the claim be dismissed, no doubt
fearful that a third adjudication was waiting in the wings.
The adjudicator took counsel's opinion and decided that, although
he did not have jurisdiction to order that the substantive claim be
dismissed, he did have jurisdiction to make an award of costs. He
ordered Parkcare to pay Roberts £87,000 plus VAT. Parkcare refused
to pay and the matter came before the Technology and Construction
Court in London.
Roberts argued that the agreement empowered the adjudicator to award
costs. In consequence, the parties to the agreement could not be taken
to have intended that the referring party could discontinue an adjudication,
perhaps just before the giving of a decision which the party believed
would be against him, thereby leaving the other party without any
remedy for the recovery of its costs. The abandonment of the claim
did not remove the jurisdiction of the adjudicator to decide the dispute
or to make an award of costs.
His Honour Judge Richard Havery QC disagreed. It was only as part
of his decision on the substantive issues that the adjudicator could
direct the payment of legal costs. That was the clear meaning of the
amended clause in the agreement between the parties. Since the adjudicator
did not make a decision on the matters set out in the notice of adjudication,
he had no jurisdiction to decide the parties' liability for costs.
Moreover, it was inappropriate to imply a term in the contract to
the effect that the adjudicator should have the power to deal with
the parties costs in such a situation. It was not necessary in order
to give 'business efficacy' to the contract and neither could the
term be implied because it represented the obvious intention of the
parties.
In consequence, Roberts' claim for costs of the discontinued adjudication
proceedings was dismissed.
- Geoff Brewer
Brewer Consulting is an independent practice providing strategic management and commercial consultancy services to the construction, oil and gas, transportation and engineering industries.
The key services we provide are:
Procurement Management
Commercial Management
Dispute Resolution
Training
The breadth of our international experience and network of professional business partners allows us to undertake assignments worldwide. |
London
Tel: +44 (0)20 7389 3800
Epsom
Tel: +44 (0)1372 727100
Northampton
Tel: +44 (0)1604 620404
Stirling
Tel: +44 (0)1786 430800
Abu Dhabi
Tel: +971 (0)2 414 6670
Dubai
Tel: + 971 4 211 5165
admin@brewerconsulting.co.uk |
|