Section 107 of the Housing Grants,
Construction & Regeneration Act has caused considerable difficulty
since the Act came into force. This part of the Act was drafted with
the intention that the provisions of the Act would only apply to written
contracts. Section 107(1) of the Act states that 'the provisions of
this Part apply only where the construction contract is in writing,
and any other agreement between the parties as to any matter is effective
for the purposes of this Part only if in writing'.
At that point, the requirements of the Act seem clear, but Section
107(2) goes on to state; 'There is an agreement in writing (a) if
the agreement is made in writing (whether or not it is signed by the
parties), (b) if the agreement is made by exchange of communications
in writing, or (c) if the agreement is evidenced in writing".
Sub-paragraph 4 adds to the potential difficulty. "An agreement
is evidenced in writing if an agreement made otherwise than in writing
is recorded by one of the parties or by a third party, with the authority
of the parties to the agreement".
The leading authority in connection with these provisions is the Court
of Appeal decision in the case of RJT Consulting Engineers v DM Engineering
(Northern Ireland). In that case, the contract had been made orally,
but written evidence of the performance of the contract was put forward
in an attempt to bring the contract within the ambit of the Construction
Act for the purposes of adjudication. Reversing the court's earlier
decision, the Court of Appeal held that invoices, minutes of meetings
and other such documentation were simply evidence of the existence
of a contract. These documents were not written evidence of the terms
of the oral agreement made between the parties. They were insufficient
to bring the contract within the ambit of the Construction Act according
to Section 107. What had to be produced was evidence in writing of
the oral agreement itself.
Lord Justice Ward held that "what has to be evidenced in writing
is literally the agreement, which means all of it, not part of it.
No doubt adjudicators will be robust in excluding the trivial from
the ambit of the agreement and the matter must be entrusted to their
common sense".
In commenting upon this ruling in the later case of Stratfield Saye
Estates v AHL Construction, Justice Jackson noted that all the express
terms of the agreement must be recorded in writing. "It is not
sufficient to show that all terms material to the issues under an
adjudication have been recorded in writing". The more recent
case of Lloyd Projects v John Malnick has further clarified this position.
Malnick engaged Lloyd, a building contractor, to convert his former
offices in Islington, London, into three residential flats. The parties
accepted that they had both reached an oral agreement in September
2003 during a telephone conversation in which Lloyd agreed to carry
out the conversion work for a lump sum price of £412,000. It
was not until February 2004, some five months later, that Lloyd wrote
to Malnick setting out his understanding of the contract, listing
items that he considered to be excluded from the lump sum price. One
week later, Malnick had replied, raising other issues in connection
with the scope of works. Throughout this time, the works had been
proceeding and interim payments made. Disputes arose and these were
referred to adjudication.
Malnick complained from the start that the adjudicator had no jurisdiction
because the contract was not in writing. Nevertheless the adjudicator
proceeded to issue his decision in which Malnick was ordered to pay
a sum in excess of £120,000 to Lloyd. Malnick refused to pay
and the matter came before the Court.
Malnick argued that the agreement was not made by the exchange of
letters between the parties, because firstly the agreement had been
made orally over five months before that exchange of correspondence,
and secondly because the correspondence in question did not contain
a concluded agreement and did not contain all of the agreed terms.
For example, the letters failed to include terms regarding the standard
of work or the scope of work. Malnick argued that only by examining
the oral evidence could a tribunal determine the terms of the contract
between the parties.
Her Honour Judge Francis Kirkham agreed that normally a contract is
made when agreement is reached. It cannot be made on more than one
occasion. "One would not normally describe a contract reached
already and then substantially performed and later recorded in writing
as a contract converted into a contract of writing". In her judgment,
the case did not fall within Section 107(2)(b). By the time of the
exchange of letters between the parties, the oral agreement was already
in existence.
Neither was Judge Kirkham persuaded that the exchange of letters adequately
identified the material terms of the agreement. The letters did not
set out who would bear the risk of unforeseen events, the standard
of work required, or the scope of works undertaken for the lump sum.
These were not trivial items but material terms of the contract which
were not evidenced in writing and accordingly it could not be said
that the contract was evidenced in writing within the meaning of Section
107.
Accordingly, Lloyd's application to enforce the decision of the adjudicator
was refused.
- Geoff Brewer
Brewer Consulting is an independent practice providing strategic management and commercial consultancy services to the construction, oil and gas, transportation and engineering industries.
The key services we provide are:
Procurement Management
Commercial Management
Dispute Resolution
Training
The breadth of our international experience and network of professional business partners allows us to undertake assignments worldwide. |
London
Tel: +44 (0)20 7389 3800
Epsom
Tel: +44 (0)1372 727100
Northampton
Tel: +44 (0)1604 620404
Stirling
Tel: +44 (0)1786 430800
Abu Dhabi
Tel: +971 (0)2 414 6670
Dubai
Tel: + 971 4 211 5165
admin@brewerconsulting.co.uk |
|