The recent case of Wimbledon Construction
Co v Derek Vago considered the circumstances in which the court might
refuse to enforce the decision of an adjudicator where the successful
party was shown to be in financial difficulties.
Wimbledon had carried out construction works to Vago's house in South
West London and disputes had arisen concerning the value of those
works. An adjudicator was appointed who published a decision, the
net effect which was to award Wimbledon the sum of approximately £120,000
inclusive of VAT. Vago refused to pay that sum and accordingly Wimbledon
commenced enforcement proceedings in the Technology and Construction
Court in London.
At about the same time as the commencement of those proceedings, Vago
commenced arbitration proceedings against Wimbledon by which he intended
to challenge many of the adjudicator's findings.
Recognising that he would have no clear defence to the enforcement
of the adjudicator's decision, Vago consented to judgment being entered
and offered to deposit the sum of £120,000 with the court to
be held pending the outcome of the arbitration. That offer was refused
by Wimbledon. Accordingly, Vago applied to the court for an order
that the enforcement of the adjudicator's decision be stayed, that
is suspended, until conclusion of the arbitration on the grounds of
Wimbledon's uncertain financial position.
His Honour Judge Peter Coulson carefully considered the previous cases
in which this issue had been examined. In Bouygues v Dahl Jensen the
Court of Appeal ordered a stay of execution of judgment enforcing
an adjudicator's decision on the grounds that Dahl Jensen were in
liquidation. Similarly, in Rainford House v Cadogan the court ordered
a stay of execution of judgment on the basis of a strong prima facie
case that the claimant was insolvent.
In three other cases however, Absolute Rentals v Glencor Enterprises,
Hershall Engineering v Breen Property and Total M & E Services
v ABB, the court refused a stay of summary judgment and allowed enforcement
of the adjudicator's decisions. Judge Coulson commented that each
case must turn on its own facts, but that it did seem however that
there were a number of clear principles which should always govern
the exercise of the court's discretion when it is considering a stay
of execution in adjudication enforcement proceedings.
He set out these principles as follows; (1) Adjudication is designed
to be a quick and inexpensive method of arriving at a temporary result
in a construction dispute. (2) In consequence, adjudicator's decisions
are intended to be enforced summarily and a claimant, being the successful
party in the adjudication, should not generally be kept out of its
money. (3) In an application to stay the execution of summary judgment
arising out of an adjudicator's decision the court must exercise the
discretion it has under the Civil Procedure Rules with the first two
considerations firmly in mind. (4) The probable inability of the claimant
to repay the sum awarded by the adjudicator may constitute 'special
circumstances' within the meaning of the Civil Procedure Pules rendering
it appropriate to grant a stay. (5) If the claimant is in insolvent
liquidation, or there is no dispute on the evidence that the claimant
is insolvent, then a stay of execution will usually be granted. (6)
Even if the evidence of the claimant's financial position suggests
that it is probable that it would be unable to repay the judgment
sum when it falls due, that would not usually justify the grant of
a stay if (a) the claimant's financial position is similar to its
financial position at the time the relevant contract was made, or
(b) the claimant's financial position is due to the defendant's failure
to pay monies awarded by the adjudicator.
Reviewing the evidence the judge concluded that Vago had not demonstrated
a probable inability on the part of Wimbledon to repay the judgment
sum if that was the outcome of the arbitration process in nine to
twelve months time.
Judge Coulson was impressed by the fact that the directors of Wimbledon
had made loans to the company which demonstrated in his view a high
degree of practical faith in the future of the business on the part
of its directors. He was also in no doubt that Wimbledon's present
financial position was the same, or very similar, to its financial
position at the time when the contract was made. Moreover, Wimbledon's
financial position appeared to be a direct result of Vago's failure
to pay the sums which were found to be due by the adjudicator.
In conclusion, summary judgment against Vago was given in the total
amount of the adjudicator's decision, including interest and costs.
- Geoff Brewer
Brewer Consulting is an independent practice providing strategic management and commercial consultancy services to the construction, oil and gas, transportation and engineering industries.
The key services we provide are:
Procurement Management
Commercial Management
Dispute Resolution
Training
The breadth of our international experience and network of professional business partners allows us to undertake assignments worldwide. |
London
Tel: +44 (0)20 7389 3800
Epsom
Tel: +44 (0)1372 727100
Northampton
Tel: +44 (0)1604 620404
Stirling
Tel: +44 (0)1786 430800
Abu Dhabi
Tel: +971 (0)2 414 6670
Dubai
Tel: + 971 4 211 5165
admin@brewerconsulting.co.uk |
|