Clause 30.9 of the JCT Standard Form
of Building Contract 1998 edition provides a rather complex set of
rules in respect of the final certificate issued by the contract administrator
at the end of the defects liability period. The clause provides that
where a final certificate has been validly issued it will operate
as conclusive evidence, firstly, that where the contract requires
it, materials and goods have been provided to a quality or standard
which meets the reasonable satisfaction of the architect, and secondly,
conclusive evidence that the contract sum has been adjusted correctly
in accordance with the contract and that all claims for extensions
of time and direct loss and expense have been finally settled.
The final certificate is therefore a critical document preventing
either party from obtaining a remedy against the other in the event
it later discovers a fault in any relevant materials or goods, or
an error in the final account computations.
There are two paths by which an exception to that position can be
obtained. Firstly, if adjudication, arbitration or other proceedings
have been commenced by either party before the final certificate has
been issued, then the final certificate will be subject to any decision,
award or judgment which flows from those proceedings. Secondly, either
party has the right to commence adjudication, arbitration or litigation
within 28 days of the issue of the final certificate. The conclusive
effect of the final certificate will then not apply to any matters
included within those proceedings. Where adjudication has been commenced
the 28 day period for commencing arbitration or litigation will run
from the date of the adjudicator's decision.
Plainly, therefore, if either the employer or the contractor is concerned
with any aspect of the final certificate it needs to move very quickly
to commence proceedings to review the disputed matter otherwise the
opportunity may be lost.
The recent case of Bennett v FMK Construction examined these provisions
where the contractor disputed the validity and the correctness of
the final certificate. The final certificate had been issued on 11
March 2005. FMK issued a notice of intention to adjudicate the amount
contained within the certificate 26 days later on 6 April 2005. 7
days later FMK applied to the Royal Institute of British Architects
for the nomination of an adjudicator. An adjudicator was nominated
the following day and the referral notice issued to him 3 days later.
At this point Bennett complained to the adjudicator that his appointment
was invalid in that, in breach of the contract, it had not been secured
within 7 days of the date of the notice of intention to refer. The
adjudicator agreed and promptly resigned. The following day, 22 April,
FMK re-served the notice of intention to refer and re-applied to the
RIBA for the appointment of an adjudicator. The same adjudicator was
appointed 4 days later.
To sum up the situation that now prevailed, starting from the date
of the issue of the final certificate and bearing in mind the 28 day
deadline, the first notice of intention to adjudicate had been served
on day 26; the first nomination of the adjudicator had occurred on
day 34; the referral notice was first communicated on day 38; the
notice of intention had been re-served on day 42; the adjudicator
reappointed on day 44 and the referral notice finally re-served on
day 46.
When all of this came before the Technology and Construction Court
the question before the court was a simple one. Had all these shenanigans
caused a situation where the final certificate would now be binding
upon the parties, the adjudication process having apparently missed
the 28 day deadline?
His Honour Judge Richard Havery Q.C. plainly took the view that having
initially given a notice of intention to adjudicate within the 28
day period, the contractor should be entitled to press on with the
adjudication to test the correctness of the final certificate. The
question was whether the precise terms of the contract admitted that
conclusion.
Firstly, Judge Havery concluded that there was no obligation to secure
the appointment of an adjudicator within 7 days of the notice of intention.
The provision contained at Clause 41A.2.2 of the contract was merely
directory and not mandatory. That being the case, the adjudicator
had had no cause to resign the first time around as his initial appointment
had been perfectly valid.
Nevertheless, having resigned, plainly the current adjudication proceedings
had not been commenced within 28 days of the issue of the final certificate.
The next question was whether the issue of the first notice of intention
to adjudicate was sufficient to comply with the contract provisions
to prevent the final certificate from being conclusive.
Bennett argued that the first notice of intention to adjudicate was
of no effect since the proceedings that flowed from that notice had
been abandoned without a decision. Judge Havery disagreed. The new
notice of intention was in the same terms as the old and it was the
same dispute or difference that was referred to the adjudicator on
the second occasion.
Relying upon clause 41A.3 of the contract Judge Havery concluded that
the adjudicator had been unavailable to adjudicate by reason of his
resignation. Once he had been reappointed, however, his appointment
effectively flowed from the first notice of intention to adjudicate.
The date of that notice of intention and not the subsequent referral
itself dictated when the adjudication proceedings had been commenced
and accordingly FMK were entitled to proceed with the adjudication
to challenge the validity of the final certificate.
- Geoff Brewer
Brewer Consulting is an independent practice providing strategic management and commercial consultancy services to the construction, oil and gas, transportation and engineering industries.
The key services we provide are:
Procurement Management
Commercial Management
Dispute Resolution
Training
The breadth of our international experience and network of professional business partners allows us to undertake assignments worldwide. |
London
Tel: +44 (0)20 7389 3800
Epsom
Tel: +44 (0)1372 727100
Northampton
Tel: +44 (0)1604 620404
Stirling
Tel: +44 (0)1786 430800
Abu Dhabi
Tel: +971 (0)2 414 6670
Dubai
Tel: + 971 4 211 5165
admin@brewerconsulting.co.uk |
|