The recovery of management costs

Date 1 September 2004
Judgment Euro Pools Plc v Clydeside Steel Fabrications Ltd, Court of Session, 17 January 2003
table
The Issue Whether a claimant may be entitled to recover management costs as a head of claim.
table
Implication Where employees are required to spend time on rectification works following a breach of contract, the employer will normally be entitled to recover the cost of the wages paid to those employees together with a contribution to general overheads.





print

Resolving disputes on construction contracts is costly and time consuming. In certain cases, the time that management devotes to the dispute may also be severely disruptive to the ongoing business. The parties will therefore want to take into account the recoverability of the cost of its management and employees in connection with the dispute resolution process.

In December 2002 I reported the case of Amec Process & Energy v Stork Engineers & Contractors, which dealt with whether management time could be recovered as costs in arbitration or litigation proceedings. It was always thought that the successful parties' direct costs incurred in using its own employed staff to prepare material for the case would not be recoverable as costs in the proceedings. However, that case appeared to indicate a softening of the court's attitude in awarding costs to a successful litigant. Judge Thornton clearly felt that the Civil Procedure Rules allowed him to widen the category of employees that could be reimbursed in the event of a successful litigation. This included Amec's own personnel and agency staff which had been engaged to undertake much of the work involved in collating, analysing and presenting the primary and supporting evidence to be used by the expert witnesses.

An alternative to recovering management costs as costs of the proceedings would be to seek to recover such costs as a head of damages for breach of contract. This issue was examined in April 2003 in the case of Phee Farrar Jones v Connaught Mason.

Phee was a recruitment consultancy that had engaged Connaught to carry out some refurbishment works on its office premises. During the carrying out of those works, a flood occurred which caused extensive damage to the building. Connaught admitted liability for the flood, which caused a significant delay to the completion of the refurbishment works. As part of their claim against Connaught, Phee included a claim for 90 hours of a manager's time expended in organising a move to alternative accommodation.

It would normally be thought that managerial expenses such as this could be claimed as damages if the claimant was able to establish that, as a consequence of the other party's breach, the claimant's trading was disturbed in a way which led to the expense being incurred. In a decision which appeared to show a more restrictive approach, Judge Toulmin rejected Phee's claim. There was no evidence that income generating opportunities were lost as a consequence of the manager being required to organise the move to alternative accommodation and Phee had not demonstrated that the manager's costs were discrete expenses that would not otherwise have been incurred.

This decision appears to have been in stark contrast to the approach of Lord Drummnd Young in the Court of Session in Scotland two months earlier in the case of Euro Pools v Clydeside Steel Fabrications.

Euro Pools designed and installed machinery and pipework for the circulation, pumping, heating, filtering and treating of water in swimming pools. It had been engaged to install filtration systems for swimming pools being constructed at leisure centres in Burntisland in Fife and East Molesey in Surrey, and had subcontracted with Clydeside to fabricate and supply the filtration tanks required for each installation. These were expected to have a working life of up to forty years and critically, were to be lined internally with high build epoxy as an anti-corrosive lining. Shortly after installation it was discovered that the tank linings had failed and that the walls of the tanks were suffering widespread corrosion.

Euro Pools claimed the costs of remedial works carried out by specialist contractors they brought in, and also claimed that some of the work involved in investigating, decommissioning, and recommissioning the filters had been carried out by their own employees, who were diverted from other contracts for this purpose. This included the time and travel costs of one of its site engineers and its managing director both of whom were claimed on daywork rates. Euro Pools argued that had these employees not been engaged in the rectification works, they would have been able to earn income at higher charge out rates.

Clydeside countered that any such losses must be traced through to identifiable financial loss such as the additional cost of completing other contracts. For example, in relation to the managing director, there was no suggestion that he had been deflected from other remunerative activity. His salary would have been paid by Euro Pools whatever he did, with the result that the company incurred no extra costs simply because he had to work harder.

Lord Drummond Young rejected these arguments. He was satisfied that if employees are required to perform additional work in consequence of a breach of contract, the work in itself represents a loss to their employer. It was quite wrong to confuse establishing that loss with the quantification of the loss. The claimant was being deprived of services that its employees were otherwise engaged to carry out, and that was sufficient to establish the existence of a loss.

As to the quantification of that loss, an objectively reasonable approach was to be taken. The employer was entitled to make a charge that reflected both employment costs and overheads such as a daywork rate. Subject to providing evidence of those costs, Euro Pools was entitled to reimbursement on this basis.

- Geoff Brewer
CJ-0435

Brewer Consulting is an independent practice providing strategic management and commercial consultancy services to the construction, oil and gas, transportation and engineering industries.

The key services we provide are:
Procurement Management Commercial Management Dispute Resolution Training
The breadth of our international experience and network of professional business partners allows us to undertake assignments worldwide.
London
Tel: +44 (0)20 7389 3800

Epsom
Tel: +44 (0)1372 727100

Northampton
Tel: +44 (0)1604 620404

Stirling
Tel: +44 (0)1786 430800

Abu Dhabi
Tel: +971 (0)2 414 6670

Dubai
Tel: + 971 4 211 5165

admin@brewerconsulting.co.uk
© Brewer Consulting