19.11.08 The operation of dispute escalation provisions in construction contracts.   Ardentia Ltd v British Telecommunications Plc, EWHC 19 June 2008
12.11.08 The effectiveness of sectional completion schedules that provide for the sequential construction of work sections.   Liberty Mercian Limited v Dean & Dyball Construction Limited [2008] EWHC 2617 (TCC)
29.10.08 Whether or not a determination notice was valid when it referred to a second notice of default which was invalid.   Reinwood Limited -v- L Brown & Sons Limited [2008] EWCA Civ 1090
22.10.08 The setting aside of agreements on the basis of economic duress.   Adam Opel GmbH and Renault S.A. v Mitras Automotive (UK) Limited QBD 18 December 2007
01.10.08 The contractual effect of letters of intent and caps on liability.   Diamond Build Limited -v- Clapham Park Homes Ltd [2008] EWHC 1439 (TCC)
10.09.08 The Interest (Scotland) Act 2007   Statutory Interest in Scotland
03.09.08 Potential amendments to the statutory provisions for adjudication and payment in Construction Contracts.   The draft Construction Contracts Bill 2008
20.08.08 Do liquidated and ascertained damages constitute an exhaustive remedy for delay related losses?   Biffa Waste Services Ltd -v- Maschinenfabrik Ernst Hese GmbH [2008] EWHC 6 (TCC)
06.08.08 The assessment of damages.   Transafrik International Limited v Venus Corporation Limited [2008] EWHC 1721 (TCC)
30.07.08 When is a buyer entitled to reject goods provided by the seller?   Whitecap Leisure Limited -v- John H Rundle Limited [2008] EWCA Civ 249
23.07.08 Resolution of disputes arising out of the NHBC Guarantee Scheme.   Crest Nicholson (Eastern) Limited v Mr and Mrs Western (TCC) 16 June 2008
16.07.08 Grounds for setting aside an expert determination.   Owen Pell Limited V Bindi (London) Limited, TCC 19 May 2008
02.07.08 The potential importance of pre-contract meeting agendas/meeting minutes.   Cubitt Building and Interiors Limited -v- Richardson Roofing (Industrial) Limited [2008] EWHC 1020 (TCC)
25.06.08 Formation of Contract.   Haden Young Limited -v- Laing O’Rourke Limited TCC 8 May 2008
18.06.08 A brief comparison of the extension of time and loss and expense provisions relating to weather under the JCT and NEC contracts.   Weather events under JCT and NEC contracts
11.06.08 Whether damages based on a diminuation in value can be assessed at a date later than the date of the breach.   Charlton & Anor v Northern Structural Services Limited [2008] EWHC 66 (TCC)
04.06.08 The legally binding nature of unregulated partnering relationships.   Baird Textile Holdings Ltd -v- Marks & Spencer PLC [2001] EWCA Civ 274
28.05.08
The use and operation of retention funds.
  Bodill & Sons (Contractors) Limited v Harmail Singh Mattu, Technology and Construction Court, 30 November 2007
07.05.08
The extent of a contractor’s liability under an entire contract.
  Safe Safe Homes Limited -v- Mr and Mrs Massingham (TCC) 2007
30.04.08
Whether a notice requirement under a contract will be treated as a condition precedent to the contractor’s entitlement.
  Various
16.04.08
Whether, under a name-borrowing or agency arrangement, a party is prevented from pursuing losses incurred from the party considered to be liable for these losses.
 
London & Regional (St George's Court) Ltd v Ministry of Defence [2008] EWHC 526 (TCC)
09.04.08
A Contractor’s liability for work executed by others.
 
C J Pearce Developments Ltd -v- Oakbridge Street Mellion Building Ltd (TCC) 14 January 2002
02.04.08
Whether an employer who calls a performance bond is obliged to account to the contractor for any overpayment.
 
Spiersbridge Property Developments Limited v Muir Construction Limited, Scottish Court of Session, 14 March 2008
19.03.08
Will a Withholding Notice become invalid should the basis on which it is issued change before the final date for payment of an interim certificate?
  Reinwood Limited v L Brown & Sons Limited [2008] UKHL 12
12.03.08 Power to omit work and termination for convenience.   Abbey Developments Limited -v- PP Brickwork Limited
20.02.08 Causation and Reasonableness of Settlement.   AXA Insurance UK Plc v Cunningham Lindsey United Kingdom [2007] EWHC 3023 (TCC)
13.02.08

Liability for engaging statutory undertakers to carry out work.

 

Henry Boot Construction Limited -v- Central Lancashire New Town Development Corporation 15 BLR 1

06.02.08

After goods have been repaired is the buyer bound to accept them?

 

J & H Ritchie Ltd -v- Lloyd Ltd.  HL 7 March 2007.

23.01.08 Concurrent delays.   Follow-up to City Inn Ltd v Shepherd Construction Ltd [2007] CSOH 190
16.01.08 The recovery of solicitor's and expert consultants' fees as damages.   Blue Circle Industries PLC -v- Ministry of Defence (Ch.D 26 November 1996)
05.12.07 Brief review of the underlying philosophy of Compensation Events, and their management and implementation   Compensation Events under the ECC form of contract, NEC 3rd Edition
07.11.07 The inclusive price principle described in Hudson’s Building and Engineering Contracts, 11th Edition 1995.   The 'Inclusive Price Principle'
31.10.07 The application of compound interest to claims for late payment of a debt.   Sempra Metals Limited v Inland Revenue Commissioners.  HL 18 July 2007.

24.10.07 The consequences of a breach of the Pre-Action Protocol for Construction and Engineering Projects.  

Cundall Johnson and Partnership LLP v Whipps Cross University Hospital NHS Trust [2007], TCC, 19 September.

03.10.07 The operation of advance payment arrangements  

Olga Mirimskaya v George Evans and Dezigner Living Limited TCC 5 September 2007

19.09.07 Whether a dispute or difference capable of reference to adjudication can exist where a course of dealing had been established by a party other than the contracting party.  

John Stirling trading as M&S Contracts v Westminster Properties Scotland Limited

12.09.07 Whether sums paid out in settlements are recoverable as damages.  

John F Hunt Demolition Limited – v – ASME Engineering Limited, TCC 27 June 2007

29.08.07 The manner in which provisions for joint names insurance in construction contracts can determine risk allocation between the parties to a contract   John F Hunt Demolition v ASME Engineering, TCC 27 June 2007, and Tyco Fire & Integrated Solutions (UK) v Rolls-Royce Motor Cars, TCC 29 June 2007
15.08.07 Proposed changes to the payment provisions within the Construction Act.   2nd Consultation on proposals to amend the Construction Act
04.07.07 The direct payment of subcontractors by the employer in the event of the insolvency of the main contractor.   Sydenhams (Timber Engineering) Ltd v CHG Holdings Ltd, TCC 3 May 2007.
20.06.07 The extent to which an engineer who is employed in relation to permanent works is obliged to point out defects in temporary works to a contractor.   Hart Investments Ltd v (1) Terence Maurice Charles Fidler (T/A Terence Fidler Partnership) (2) Larchpark Ltd (in liquidation), TCC 30 March 2007.
06.06.07 Application of the express terms of the JCT contract for the termination of the contract.   Reinwood Ltd v Brown & Sons Ltd, TCC 9 November 2006.
30.05.07 The importance of critical path analysis to the delay claims.   Mirant Asia-Pacific Construction (Hong Kong) Ltd v Ove Arup & Partners International Ltd, TCC 20 April 2007.
23.05.07 Recovery of tendering costs and loss of profit and the duty of an architect to advise.   J & A Developments Ltd v Edina Manufacturing Ltd, Armoura Ltd and others [2006], NIQB 85, 11 December 2006.
02.05.07 The application of interest in the event of non-payment.   Claymore Services Ltd v Nautilus Properties Ltd, TCC 20 March 2007.
18.04.07 Title to sue and assignation (or assignment).   Laurence McIntosh Limited v Balfour Beatty Group and the Trustees of the National Library of Scotland.
04.04.07 The concept of ‘Time at large’.   Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd.  TCC 6 March 2007.
07.03.07 Examining claims for unforeseen ground conditions.   General.
14.02.07 Whether the employment costs of staff are recoverable as damages.   Aerospace Publishing Limited v Thames Water Utilities Limited, CA, 11 January 2007.
07.02.07 Review of some of the mechanisms currently in use to reduce conflict on construction projects.   General consideration of Dispute Avoidance.
31.01.07 Questions of law concerning (1) whether defective design or defective workmanship was the operative cause of defects in a roof and (2) whether a main contractor can assume liability for design work carried out by a nominated sub-contractor.   Sinclair v Woods of Winchester Ltd (no 2), TCC 22 November 2006.
24.01.07 Interpreting the intent of parties to an agreement.   Skanska Rashleigh Weatherfoil v Somerfield Stores Ltd, 22 November 2006 (CA).
06.12.06 Examining clauses in contracts of sale that provide for retention of title until full payment is made.   Various.
22.11.06 The use of without prejudice protection to prevent the use of mediation documents in subsequent litigation.   Aird v Prime Meridian Limited, 19 September 2006, TCC.
01.11.06 The common law defence of abatement.   Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd, TCC 5 June 2006.
25.10.06 The principal grounds upon which a petition presented to the High Court for winding up under section 124(1) of the Insolvency Act 1986 may be avoided.   Medlock Products Limited v SCC Construction Limited, Bristol High Court, 13 July 2006, Seawind Tankers Corporation v Bayoil SA (1998), CA.
18.10.06 The wording of settlement agreements.   Carlo Mantegazza & Anor v Neil Holland Architects & Anor, TCC, 11 May 2006..
11.10.06 When interest is payable upon a claim.   Various.
27.09.06 The battle of the forms, exclusion clauses, and guidance to experts.   Balmoral Group Ltd v Borealis Group Ltd and (1) Borealis [UK] Ltd (2) Borealis AS (3) Borealis A/S.
20.09.06 Interpreting the intent of parties to an agreement.   Skanska Rashleigh Weatherfoil v Somerfield Stores Ltd, 28 April 2006 (TCC).
06.09.06 Identifying the various types of dispute board and the advantages which may be brought.   General discussion of dispute boards.
23.08.06 Examining the rules for the interpretation of oral contracts.   Brian Royle Maggs v Guy Marsh & Others, CA 7 July 2006.
16.08.06 Can a party who is assigned rights under a contract recover more from the contract-breaker than the assignor could have done had there been no assignment.   Larkstore Ltd v Technotrade Ltd, Court of Appeal, 27 July 2006.
09.08.06 Using the Contracts (Rights of Third Parties) Act 1999.    
02.08.06 The administration of provisional sums within a construction contract.   Midland Expressway v Carillion Construction & Others, CA 15 June 2006.
19.07.06 The obligations placed upon Arbitrators in respect of bias.   Norbook Laboratories Ltd v (1) A Tank (2) Moulson Champlant Ltd, (TCC) 12 May 2006.
14.06.06 The effect of defects upon a quantum meruit valuation.   ERDC Group Limited v Brunel University, TCC 29 March 2006.
07.06.06 Whether settlement agreements can be used to ascertain loss in the context of subsequent insurance claims.   Enterprise Oil Limited v Strand Insurance Company Limited, QBD 26 January 2006.
31.05.06 The extent of an engineering designer’s duties to verify its initial design assumptions.   Ove Arup & Partners International Limited v Mirant Asia-Pacific Construction (Hong Kong) Limited, CA 21 December 2005.
17.05.06 The effect of the HGCRA on the JCT insolvency provisions.   Melville Dundas Ltd v George Wimpey UK Ltd [2005], Inner House Court of Session, 15 December 2005.
03.05.06 Whether a contractor can apply a set-off of monies owed under the building contract to defeat a claim under a collateral warranty.   Safeway Stores Limited v Interserve Project Services Limited, TCC 1 December 2005.
19.04.06 The quantification of loss in cases of professional negligence.   Plymouth & South West Co-operative Society Limited v Architecture, Structure & Management Limited, TCC, 10 January 2006.
05.04.06 The requirement for impartiality and independence of the decision maker under construction contracts.   Scheldebouw BV v St James Homes (Grosvenor Dock) Ltd, TCC 16 January 2006.
08.03.06 Whether an arbitration notice issued under an ICE contract has to comply strictly with the arbitration code incorporated within the contract.   Scrabster Harbour Trust v Mowlem plc, Inner House Court of Session 22 February 2006.
01.02.06 Whether terms within a standard PFI building contract contravene the requirements of the HGCRA.   Midland Expressway Ltd v Carillion Construction Ltd & Others, TCC 24 November 2005.
25.01.06 Potential amendments to the Construction Act to improve payment practices in the construction industry.   Review of the DTI consultation into the operation of the HGCRA, published 16 January 2006.
18.01.06 Cases of significance or interest over the past 10 years.   Various.
11.01.06 Whether the courts will uphold express obligations between the parties to negotiate in good faith.   Petromec Inc v Petroleo Brasileiro SA, CA 15 July 2005.