Date Issue   Judgment
20.08.08 Do liquidated and ascertained damages constitute an exhaustive remedy for delay related losses?   Biffa Waste Services Ltd -v- Maschinenfabrik Ernst Hese GmbH [2008] EWHC 6 (TCC)
13.08.08 The extent to which a party may make representations to an adjudicator nominating body about the suitability of a particular adjudicator.   Makers UK Limited v The Mayor and Burgesses of The London Borough of Camden, TCC, 25 July 2008
06.08.08 The assessment of damages.   Transafrik International Limited v Venus Corporation Limited [2008] EWHC 1721 (TCC)
30.07.08 When is a buyer entitled to reject goods provided by the seller?   Whitecap Leisure Limited -v- John H Rundle Limited [2008] EWCA Civ 249
23.07.08 Resolution of disputes arising out of the NHBC Guarantee Scheme.   Crest Nicholson (Eastern) Limited v Mr and Mrs Western (TCC) 16 June 2008
16.07.08 Grounds for setting aside an expert determination.   Owen Pell Limited V Bindi (London) Limited, TCC 19 May 2008
09.07.08 Liquidated and Ascertained Damages.   Braes of Doune Wind Farm (Scotland) Limited and Alfred McAlpine Business Services Limited [2008] EWHC 426 (TCC)
02.07.08 The potential importance of pre-contract meeting agendas/meeting minutes.   Cubitt Building and Interiors Limited -v- Richardson Roofing (Industrial) Limited [2008] EWHC 1020 (TCC)
25.06.08 Formation of Contract.   Haden Young Limited -v- Laing O’Rourke Limited TCC 8 May 2008
18.06.08 A brief comparison of the extension of time and loss and expense provisions relating to weather under the JCT and NEC contracts.   Weather events under JCT and NEC contracts
11.06.08 Whether damages based on a diminuation in value can be assessed at a date later than the date of the breach.   Charlton & Anor v Northern Structural Services Limited [2008] EWHC 66 (TCC)
04.06.08 The legally binding nature of unregulated partnering relationships.    Baird Textile Holdings Ltd -v- Marks & Spencer PLC [2001] EWCA Civ 274
28.05.08
The use and operation of retention funds.
  Bodill & Sons (Contractors) Limited v Harmail Singh Mattu, Technology and Construction Court, 30 November 2007
21.05.08
The withholding of liquidated damages from a sum directed to be paid by an adjudicator.
  Avoncroft Construction Limited v Sharba Homes (CN) Limited, TCC, 29 April 2008
14.05.08
The extent of an arbiter’s implied powers in Scottish arbitrations.
  Apollo Engineering Limited v James Scott Limited [2008] CSOH 39
07.05.08
The extent of a contractor’s liability under an entire contract.
  Safe Safe Homes Limited -v- Mr and Mrs Massingham (TCC) 2007
30.04.08
Whether a notice requirement under a contract will be treated as a condition precedent to the contractor’s entitlement.
  Various
23.04.08
The extent to which an adjudicator’s decision is severable, or may be partially enforced.
  Cantillon Limited v Urvasco Limited, TCC, 27 February 2008
16.04.08
Whether, under a name-borrowing or agency arrangement, a party is prevented from pursuing losses incurred from the party considered to be liable for these losses.
 
London & Regional (St George's Court) Ltd v Ministry of Defence [2008] EWHC 526 (TCC)
09.04.08
A Contractor’s liability for work executed by others.
 
C J Pearce Developments Ltd -v- Oakbridge Street Mellion Building Ltd (TCC) 14 January 2002
02.04.08
Whether an employer who calls a performance bond is obliged to account to the contractor for any overpayment.
 
Spiersbridge Property Developments Limited v Muir Construction Limited, Scottish Court of Session, 14 March 2008
26.03.08
The extent to which an adjudicator has jurisdiction to decide the ramifications of a new defence.
  Cantillon Limited v Urvasco Limited, TCC, 27 February 2008
19.03.08
Will a Withholding Notice become invalid should the basis on which it is issued change before the final date for payment of an interim certificate?
  Reinwood Limited v L Brown & Sons Limited [2008] UKHL 12
12.03.08 Power to omit work and termination for convenience.   Abbey Developments Limited -v- PP Brickwork Limited
05.03.08

Was the Enforcement of an adjudicator’s decision made in favour of a subcontractor subject to set off arising from a pain and gain regime?

 

Ledwood Mechanical Engineering Ltd-v-Whessoe Oil and Gas Ltd & Volker Stevin Construction Europe BV, TCC 20 November 2007

27.02.08

What's new in the 2007 form of this contract?

 

The JCT Framework Agreement 2007

20.02.08
Causation and Reasonableness of Settlement.
 
AXA Insurance UK Plc v Cunningham Lindsey United Kingdom [2007] EWHC 3023 (TCC)
13.02.08

Liability for engaging statutory undertakers to carry out work.

 

Henry Boot Construction Limited -v- Central Lancashire New Town Development Corporation 15 BLR 1

06.02.08

After goods have been repaired is the buyer bound to accept them?

 

J & H Ritchie Ltd -v- Lloyd Ltd.  HL 7 March 2007

30.01.08
Whether notices are a condition precedent to entitlement to extensions of time.
 
Steria Limited v Sigma Wireless Communications Ltd, TCC 15 November 2007
23.01.08
Concurrent delays.
 
Follow-up to City Inn Ltd v Shepherd Construction Ltd [2007] CSOH 190
16.01.08
The recovery of solicitor's and expert consultants' fees as damages.
 
Blue Circle Industries PLC -v- Ministry of Defence (Ch.D 26 November 1996)
09.01.08
The importance of critical path analysis to delay claims.
 
City Inn Ltd v Shepherd Construction Ltd [2007] CSOH 190