| Date |
Issue |
|
Judgment |
47 cases found.
| 14.12.2005 |
Resolving multi party disputes in arbitration. |
|
City & General (Holborn) Ltd v AYH plc, TCC 29 September 2005 |
| 07.12.2005 |
The payment of indemnity costs by the unsuccessful party in litigation. |
|
Wates Construction Ltd -v- HGP Greentree Allchurch Evans Ltd, TCC 10 October 2005 |
| 30.11.2005 |
Terminating a subcontract on the grounds of delay when the contractor's obligation is to complete the works within a reasonable time. |
|
Shawton Engineering Ltd -v- DGP International Ltd and Others, CA 18 November 2005 |
| 23.11.2005 |
Noise nuisance between adjoining occupiers of apartments. |
|
Leslie Arthur Stannard v Al Sharekh and Others, QBD 29 July 2005 |
| 16.11.2005 |
The status of building services design drawings and responsibility for coordination. |
|
Emcor Drake & Scull Ltd -v- Edinburgh Royal Joint Venture and others, Court of Session, 28 October 2005 |
| 09.11.2005 |
The importance of managing and controlling electronic data in the event of future disputes. |
|
Practice Direction 31 of the Civil Procedure Rules - Disclosure of Documents, 29 September 2005 |
| 02.11.2005 |
The tort of nuisance and the duties of chartered surveyors. |
|
Panesh Mistry -v- Mr and Mrs Thakor and Michael Roberts, CA 5 July 2005 |
| 26.10.2005 |
The incorporation of express terms by reference. |
|
Machenair Ltd -v- Gill and Wilkinson Ltd, TCC 14 March 2005 |
| 19.10.2005 |
Whether a contractor can take advantage of its own breach of contract to rely upon a contractual provision for the capping of damages. |
|
Decoma UK Ltd v Haden Drysys International Ltd, TCC 27 July 2005 |
| 12.10.2005 |
Nomination of an adjudicator. |
|
Palmac Contracting Limited -v- Park Lane Estates Limited, TCC 22 March 2005 |
| 05.10.2005 |
Obtaining a mandatory injunction to remove a building built in breach of a restrictive covenant. |
|
Mortimer -v- Bailey CA, 29 October 2004 |
| 28.09.2005 |
Examining the extent of duties imposed by construction management. |
|
Great Eastern Hotel Co Ltd v John Laing Co Ltd, TCC 24 February 2005 |
| 21.09.2005 |
The accrual of causes of action in respect of claims for additional payment under a construction contract. |
|
Birse Construction Ltd v McCormick (UK) plc, CA 26 July 2005 |
| 14.09.2005 |
The admissibility of evidence of negotiations in construing the meaning of a written contract. |
|
Peter Stroude v Beazer Homes Ltd, CA 17 March 2005 |
| 07.09.2005 |
Incorporation of terms by reference to a standard form of contract where it is intended that a formal contract will be drawn up in the future. |
|
Bryen & Langley Limited -v- Martin Boston, TCC 29 July 2005 |
| 31.08.2005 |
Payment of parties' costs in the event of a discontinued adjudication. |
|
John Roberts Architects Ltd -v- Parkcare Homes (No 2) Ltd, TCC 25 July 2005 |
| 24.08.2005 |
Whether oral contracts may be subject to the provisions of the Construction Act. |
|
Lloyd Projects Ltd -v- John Malnick, TCC 22 July 2005 |
| 10.08.2005 |
The operation of deeming provisions and reference to working days. |
|
Lafarge (Aggregates) Ltd -v- Newham Borough Council, QBD 24 June 2005 |
| 03.08.2005 |
Structuring adjudication referrals to achieve payment. |
|
Geris Handelsgesellschaft GmbH -v- Les Construction Industrielles de la Mediterrannee SA, 11 February 2005 |
| 27.07.2005 |
Whether the court will uphold an agreement to agree. |
|
Willis Management (Isle of Man) Ltd -v- Cable & Wireless plc and Pender Insurance Ltd, CA 30 June 2005 |
| 20.07.2005 |
Application of the Limitation Act to payment claims. |
|
Henry Boot Construction Ltd v Alstom Combined Cycles Ltd, CA 4 July 2005 |
| 13.07.2005 |
Commencing adjudication proceedings following the issue of a final certificate under a JCT contract. |
|
Tracy Bennett v FMK Construction Limited, TCC 30 June 2005 |
| 06.07.2005 |
Applying the terms of letters of intent. |
|
Mowlem plc v Stena Line Ports Ltd, TCC 6 October 2004 |
| 29.06.2005 |
Duties of a project manager under the NEC contract. |
|
Costain Ltd & Others v Bechtel Ltd, TCC 20 May 2005 |
| 22.06.2005 |
Interpretation of liquidated damages provisions and whether they represent a penalty. |
|
Alfred McAlpine Capital Projects Ltd v Tilebox Ltd, TCC 25 February 2005 |
| 15.06.2005 |
Use of the expression "all direct costs and directly incurred losses". |
|
Robertson Group (Construction) Ltd v Amey-Miller (Edinburgh) Joint Venture, Outer House Court of Session, 10 May 2005 |
| 08.06.2005 |
Objections under the Telecommunications Act 1984 for the siting of mobile telephone communications masts. |
|
Petursson v Hutchison 3G UK Limited, TCC 9 May 2005 |
| 01.06.2005 |
Whether an adjudicator's decision delivered late will remain binding upon the parties. |
|
Ritchie Brothers (PWC) Ltd v David Philp (Commercials) Ltd, Inner House, Court of Session 24 March 2005 |
| 25.05.2005 |
Principles underlying the enforcement of adjudicator's decisions. |
|
Carillion Construction Ltd v Devonport Royal Dockyard, TCC 26 April 2005 |
| 18.05.2005 |
Interpreting the provisions of a contractor's all-risk policy. |
|
Horbury Building Systems Limited v Hampden Insurance NV, CA 7 April 2004 |
| 11.05.2005 |
The measure of damages for defective building works. |
|
Birse Construction Ltd v Eastern Telegraph Co Ltd, 5 November 2004 |
| 04.05.2005 |
Payment of costs where there are separate awards in respect of claim and counterclaim. |
|
Burchell v Bullard, Court of Appeal 8 April 2005 |
| 27.04.2005 |
Potential changes in the legislation following experience of the Construction Act since May 1998. |
|
Consultation into the adjudication provision of the Housing Grants Construction and Regeneration Act |
| 13.04.2005 |
Whether there is any limit to the timescale within which an adjudication may be commenced. |
|
Connex South Eastern Ltd v MJ Building Services plc, CA 1 March 2005 |
| 06.04.2005 |
Whether an arbitration notice issued under an ICE contract has to comply strictly with the arbitration code described at clause 67(2) of the conditions. |
|
Scrabster Harbour Trust v Mowlem plc, Outer House, Court of Session 23 March 2005 |
| 30.03.2005 |
The manner in which an engineer is required to make a decision under clause 66 of the ICE Conditions prior to the commencement of arbitration. |
|
Amec Civil Engineering Limited v The Secretary of State for Transport, CA 17 March 2005 |
| 23.03.2005 |
Circumstances in which disputed matters should be decided according to the "burden of proof". |
|
Stephens v Cannon, CA 14 March 2005 |
| 16.03.2005 |
Whether a responding party can submit new material in its response to adjudication. |
|
William Verry (Glazing Systems) v Furlong Homes Ltd, TCC 13 January 2005 |
| 09.03.2005 |
Whether a notice requirement under a contract will be treated as condition precedent to the contractor's entitlement. |
|
Bremer Handelgesellschaft mbH v Vanden Avenne Izegem nv, House of Lords (1978) |
| 02.03.2005 |
The application of the term "without prejudice". |
|
Schering Corporation v Cipla Limited, High Court 10 November 2004 |
| 02.03.2005 |
The application of the "prevention principle" in rebutting claims for liquidated damages. |
|
Gaymark Investments Pty Limited v Walter Constructions Group, NTSC 20 December 1999 |
| 16.02.2005 |
Examining the question of remoteness of damages for breach of contract. |
|
Jackson v Royal Bank of Scotland, House of Lords 26 January 2005 |
| 09.02.2005 |
Whether the failure to serve a withholding notice may lead to the conclusion that there is no dispute capable of being referred to arbitration or adjudication. |
|
Collins (Contractors) Ltd v Baltic Quay Management (1994) Ltd, Court of Appeal 7 December 2004 |
| 02.02.2005 |
Whether a duty of care in tort exists between a subcontractor or sub-consultant and the employer. |
|
Architype Projects Ltd v Dewhurst Macfarlane & Partners, TCC 18 December 2003 |
| 26.01.2005 |
Entitlement to payment on a quantum meruit basis under the principle of restitution. |
|
Mowlem plc v PHI Group Ltd, TCC 28 July 2004 |
| 19.01.2005 |
Whether an architect or engineer has authority to bind its client into contract with a contractor. |
|
GPN Limited (In Receivership) v O2 (UK) Limited, TCC 22 October 2004 |
| 12.01.2005 |
Negotiation of subcontract terms whilst the works are proceeding. |
|
Emcor Drake & Scull v Sir Robert McAlpine, CA 21 December 2004 |
|
|
|
|
|
|